Forest Glen Station

Evaluation Metric Measure
Access to Key Destinations i
Two green up arrows

Significantly improves Access to Key Destinations

Click here to see more information on this capital metric and its measures.

Accessibility Improvement(s) i
Two green up arrows

Makes assets fully accessible

Click here to see more information on this capital metric and its measures.

Asset Condition (FTA TERM Rating) i
Yellow gear

Asset(s) rated 2-3

Click here to see more information on this capital metric and its measures.

Benefit to Riders i
Two green up arrows

Significant benefit to riders

Click here to see more information on this capital metric and its measures.

Capacity Benefit and Need i
One green up arrow

Project increases capacity of transit operations not near capacity

Click here to see more information on this capital metric and its measures.

Climate Agency Operating Impacts i
Not applicable symbol

Project does not effect GHG emissions

Click here to see more information on this capital metric and its measures.

Economic Impact i
Not applicable symbol

No economic impact

Click here to see more information on this capital metric and its measures.

Equity Based on Residential Geography i
One green up arrow

Score 0-2 in Justice40 metric 'Sum of Disadvantage Indicators'

Click here to see more information on this capital metric and its measures.

Impact on Customer and Employee Safety i
One green up arrow

Project indirectly provides safety benefit/improvement

Click here to see more information on this capital metric and its measures.

Impact on Operating Cost i
Black line with arrows on each end

No change in operating cost

Click here to see more information on this capital metric and its measures.

Impact on System Security i
Two green up arrows

Project implements new security protection and/or prevention

Click here to see more information on this capital metric and its measures.

Impact to Service Speed/Reliability i
Not applicable symbol

No impact on service speed/reliability

Click here to see more information on this capital metric and its measures.

Regulatory Requirements i
Black x mark

No regulatory requirements met for this project

Click here to see more information on this capital metric and its measures.

Ridership/Mode Shift Impacts i
Two green up arrows

Significantly improves transit ridership

Click here to see more information on this capital metric and its measures.

Vehicle Useful Life i
Not applicable symbol

Asset is not a vehicle with a useful life

Click here to see more information on this capital metric and its measures.

Project Description

The Forest Glen Station will undergo a multi-phase rehabilitation. Phase 1 will replace the inbound and outbound platforms with new heated platforms that will include tactile strips for ADA compliance, reconstruct the entry staircase with heated stairs, and replace the deficient and outdated station depot with a temporary shelter. Following design engineering services, Phase 2 will add a new, heated station depot to replace the temporary shelter. New wayfinding signage and other station identifiers will be added as well. Upon completion of Phase 3, the station will be made fully ADA-accessible with the installation of a ramp or elevator and potential pathway improvements, along with other necessary ADA compliance measures.