Bellwood Metra Station Access Improvements
This project funds phase II engineering and construction to remove and replace curb ramps and blended sidewalk areas to comply with ADA standards in 21 locations within the Village. Improvements will consist of removing and replacing sidewalks, curb ramps and curbs, adjusting frames/grates to meet final grade, Hot-mix asphalt pavement patching will be utilized to restore pavement areas. Thermoplastic pavement marking and landscape restoration shall also occur as part of this improvement. Locations selected focus on those areas traveled by residents to access the Metra Bellwood station and Pace bus stops within the Village.
The Phase I engineering report has been submitted for IDOT for review and approval.
Source | Amount |
---|---|
Federal | $120,798 |