Richton Park Metra Station and Pace Route Access Improvements
Description
Project improvements include crosswalks, sidewalk connectors, ADA accessibility improvements at the Richton Park Metra station and along Pace Route #362.
Current Activities
Construction of this project is complete. Awaiting IDOT closeout.
Project Type
Pedestrian Access to Transit
Project Year
Project Status
Completed
Grantee
Richton Park
Planning Program
Access to Transit Program
Funding Amounts by Source
Source | Amount |
---|---|
RTA | $70,401 |
Federal | $281,602 |
Last Updated 06.24.2022