North Central Service Analysis and Implementation Study
Description
This study created a coordinated sub-regional investment plan framework focused on the communities served by the Metra North Central Service. Project initiatives identified planned enhancements to the line and service enhancements preferred by existing riders, outlined implementation strategies, identified traditional and non-traditional funding sources for infrastructure improvements, and provided parameters for legal authority to move forward.
Current Activities
The project was completed in February of 2020 and adopted by the Mundelein Village Board in April of 2020. The RTA, Village and the Lake County Transportation Alliance are identifying a strategy to move forward with recommendations of the plan.
Related Reports
Project Type
Transit Improvement Plan
Project Year
Project Status
Completed
Grantee
Mundelein
Planning Program
Community Planning
Funding Amounts by Source
Source | Amount |
---|---|
RTA | $50,000 |
Local | $25,000 |
Federal | $50,000 |
Last Updated 05.01.2020