Kane County Ride-in-Kane Assessment

Description
This project assessed the existing Ride in Kane program and recommended areas of improvement. Program performance and financial conditions were examined. Solution strategies of the report focus on elements such as trip scheduling, reporting procedures, and trip pooling. An implementation plan and sponsor toolkit resource guide were prepared to assist program participants in enacting recommendations.
Current Activities
The final report was completed in October, 2015.

Project Type
Transit Improvement Plan
Project Year
Project Status
Completed
Grantee
Kane County DOT
Planning Program
Community Planning
Funding Amounts by Source
Source Amount
Local $15,000
Federal $60,000
Last Updated 10.05.2016