Midlothian Metra Station Access Improvements

Description

This project consisted of access improvements in the Midlothian Metra station area including removal and replacement of 8,542 square feet of sidewalk, installation of 1,268 feet of crosswalks, installation of ADA handicapped panels/ detectable warnings at 68 locations, and pedestrian lighting improvements on 147th Street from Pulaski to Central Park.

Current Activities

Construction of this project is complete.


Project Type
Pedestrian Access to Transit
Project Year
Project Status
Completed
Grantee
Midlothian
Planning Program
Access to Transit Program
Funding Amounts by Source
Source Amount
RTA $196,000
Federal $784,000
Last Updated 01.10.2022