Hoffman Estates Pace Barrington Road Station Improvements
This project will construct a new off-road shared-use path on the north side of Central Road from the existing Paul Douglas Forest Preserve path system to the Pace Park-n-Ride at Barrington Road. The path will be 10 feet wide located generally along the right of way on the north side of Central Road. Destination and distance signing along with traffic controls for intersection and driveway crossings are included. Signal upgrades and modifications at the Central Road / Huntington Boulevard intersection will be made for bicycle and pedestrian users.
Phase II Design Engineering has commenced with the Cook County Department Of Transportation and Highways and is nearing completion. Anticipated letting in July 2025.
Source | Amount |
---|---|
RTA | $67,500 |
Local | $67,500 |
Federal | $540,000 |