Project Management Oversight (PMO) Capital Projects
The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently. The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.
Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.
PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site. The latest report is the December 2024 Project Management Oversight report.
Toggle | Agency | Project Title | Asset Category | Mode | 2025 Funding | 2025-2029 Funding | Status | ||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
+ | CTA | Red Line Extension | Extension | Rail | $612,109,069 | $3,955,980,297 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
The Red Line Extension project extends south end of line 5.6 miles and will include four new, fully accessible stations at 103rd Street, 111th Street, Michigan Avenue, and 130th Street. Provides for a share of funding necessary to advance from the engineering to construction phase of project schedule to start in early 2025.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
This is a design build project that is currently in the design phase. The design is divided into 5 segments. The contractor is working on the development of the geotechnical plans and packages for all segments. Segments 1,2,3, and 130th street are having comments from CTA addressed in the intermediate stage. Segments 4 and 5 are continuing with the field drilling and analysis. The Guideways of Segment 5 is in the concept design phase, while Segments 1, 2, 3 and 4 have moved on the intermediate design phase. Guideway Segment 4 is with UPRR for review. All 4 of the station concept designs are with CTA for review, with expected comments returned by June 2025. The 130th bridge design continues, including coordination with IDOT as it is to be built to their standards. The stormwater management report concept was submitted to the CTA for review, and the Civil Utility Plans are in the intermediate design stage. The Yard and Shop design has reached the 60% milest
Last Updated 06.10.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | CTA | Replace Buses - Options to Purchase Up To 500 of 1,030 | Rolling Stock | Bus | $74,570,219 | $74,570,219 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
The scope of this project will provide for the engineering, purchase, and inspection of fully accessible, air conditioned Clean Diesel buses; including a spare parts inventory. Engineering includes: development of specifications, pre-bid engineering meetings, onsite inspections of prospective bidders and/or their vendors’ plants, inspection of buses during production and acceptance of vehicles after delivery. 5 Year funds will continue funding stream for the Option(s) to replace up to 500 additional buses. Option(s) to the Base (100) contract order consist of up to an additional 500 buses that will initiate multiple orders to replace the 1000 Series New Flyer buses that have been in service since FY 2006.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
As of April 2025, all 500 buses from the base order, Option 1, 2, 3, and 4 have been delivered and placed in service. Under Option 5, all 100 buses have been delivered and 78 have been placed in service. Punch list items remain and warranty period is ongoing for production buses with final invoices remaining. This will be the final update on this project.
Last Updated 06.10.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | CTA | Ventra 3.0 Upgrade | Support Facilities & Equipment | System | $58,376,336 | $58,376,336 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Funding will provide for the complete overhaul of the Open Standards Fare System (OSFS), called Ventra. This will be the first major overhaul of this complex technology tool in nearly 10 years. The Ventra system was initially launched in 2013/2014 and since that time, fare collection technology has drastically improved, due in large part of the Ventra system. The Ventra upgrade or Ventra 3 project will move CTA, Pace and Metra onto a modern, open architecture platform that harnesses technology enhancements and fare system advancements from the past ten years.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Formal QA testing is ongoing and is 93% complete. Testing will then move to the “Day in the Life” phase testing to simulate normal operation conditions to test for defects. Next, it will move to pilot testing and then go-live.
Last Updated 06.10.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Zero-Emissions Trainsets | Rolling Stock | Rail | $44,024,137 | $220,900,000 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Metra's investment in innovative, cleaner energy locomotives will be funded in part by this project which will procure multiple-unit railcar trainsets that produce zero mobile emissions. This multi-year, multi-phase project will acquire battery-electric trainsets. Metra seeks to be among the first passenger rail transit agencies to purchase and operate self-propelled trainsets that will not require the construction and maintenance of wayside power. Metra estimates that replacing one old diesel locomotive with a zero-emission locomotive will reduce nitrogen oxide (NOx) emissions by more than 30 tons per year. This project will significantly reduce emissions, improve local air quality, greatly reduce operational costs, and lower maintenance costs.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Metra put the bid on the street in May 2022 and was awarded to Stadler US, Inc.. The contract consists of eight trainsets for the base order. Preliminary design review activities are expected to begin soon and follow-up with various component and sub-component designs.
Last Updated 06.10.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Pace | Fixed Route Electric Buses | Rolling Stock | Bus | $36,000,018 | $173,949,056 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Replacement battery-electric buses including associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections) for fixed route services operating systemwide.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The contract was executed, and the vendor originally provided Pace with an updated production schedule due to previous supply chain issues and long lead time items. However, the vendor was bought out by a new company, Phoenix Cars, LLC. Since the change, Phoenix has provided Pace with an updated delivery schedule. Production of the buses will start by July 2025 and delivery to begin in Q4-2025 and last vehicle is expected to be delivered in Q1-2026.
Last Updated 06.10.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Program Management | Contingencies and Administration | Rail | $34,806,375 | $123,441,392 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project will fund the professional services necessary to deliver capital projects. Project activities may include but are not limited to funding studies, concept design, developing new business tools and processes, professional services under the Project Management Oversight (PMO) contract, and the procurement of software. Historic levels of capital funding necessitate additional program management capacity.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The project management oversight contract was awarded to WSP. WSP and Metra staff are working through the process to support delivery of Metra’s Capital Program. Purchase Order Releases have been approved and work is in progress on various capital projects.
Last Updated 06.10.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | CTA | Purchase Rail Cars - 7000 Series (Base Order 400) | Rolling Stock | Rail | $30,334,196 | $30,334,196 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Purchase Rail Cars - 7000' Series (Base Order 400) - Program funds will provide for the continued cash needs and obligation provisions as identified in the contract documents for the 7000' series rail car Base contract order of 400 cars.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Status conferences continued with CRRC to address/track various items. Production deliveries continued during this reporting period. CTA inspection personnel continue working in China and continue to conduct welded subassembly checks and production car body shell inspections for production cars. There are 69 car body shells in various stages of assembly or being delivered to Chicago. Final assembly is ongoing on 33 cars in the US with 24 cars are currently in final inspection at Skokie Shops. CTA has accepted 180 cars for revenue service out of 204 delivered.
Last Updated 06.10.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Van Buren St. Station | Stations & Passenger Facilities | Rail | $24,485,250 | $24,485,250 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
A complete renovation of the downtown Chicago terminal station will rehabilitate the existing historic waiting rooms, replace the roof assembly while maintaining the green roof, and will replace the pedestrian tunnel in the park. A new 'pop-up' entrance in Grant Park will add a new access stair case and elevator and add an ADA-compliant ramp connecting to the pedestrian bridge. The pedestrian tunnel under Michigan Ave will be waterproofed and a new elevator will be added to the Jackson Blvd platform. The scope of work includes rehabilitation of the stair enclosures and elevator west of Michigan Avenue, replacement of the platforms, new full-length platform canopies, heated warming shelters, construction of a new vendor space at lower level, and all new mechanical, electrical, and plumbing throughout the station.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Metra awarded the consultant contract for station concept design. The concept design is at 15% completion and on hold pending completion of lakefront ordinance protection, NEPA, and environmental processes. Documents are being prepared to be submitted to lakefront ordinance for approval. Environmental and NEPA work is ongoing. There was a solicitation for a new LIQ blanket for design services to get the design from 10% to 30% and then a separate solicitation from 30% to 100%. The design is expected to be completed in Q1-2027.
Last Updated 06.10.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Smart Gates | Electrical, Signal & Communications | Rail | $22,000,000 | $24,000,000 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project involves upgrades to protected grade crossings to improve the safety and reliability of grade crossing protections. Metra has approximately 300 active grade crossings with warning devices. This project will fund upgrades of circuitry at these grade crossings to the latest technology. Metra will install monitors to check the condition of the grade crossing protection system. When a monitor detects an anomaly, the system will send a notice to the back office and dispatch a signal maintainer to perform repairs. PTC Wireless crossings are being added to the scope in 2025 and beyond.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The construction and software installation on the first 14 crossings has been completed. The software consultant is finalizing the configuration of the communication with the back office. Metra was selected to receive an FRA Rail Crossing Elimination grant that will fund the installation of additional 36 smart gate crossings with a PAYGO funding local match.
Last Updated 06.10.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Pace | River Division Electrification/Expansion | Support Facilities & Equipment | Bus | $20,250,000 | $82,040,000 | Behind Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Renovation of River Division located in Elgin, more than doubling the garage’s current capacity, including office space and installation of charging capabilities for electric buses.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Pace has entered into a contract for Architectural and Engineering services for pre-design and design services. The contractor completed the pre-design activities, and final pre-design report was submitted to Pace. The adjacent property acquisition has been completed. Pace has completed a Change Order to the design contract to include additional scope for the electrification component. The design activities with the additional scope for electrification are ongoing. The final 30% design is scheduled to be submitted to Pace at the end of May 2025.
Last Updated 06.10.2025 |