Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the December 2024 Project Management Oversight report. 

i

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Project Title Asset Category Mode 2025 Funding 2025-2029 Funding Status
+ CTA Purchase up to 70 Electric Buses and up to 9 Charging Stations Rolling Stock Bus $0 $0 On Schedule

Project Details

Description
Purchase up to 70 Electric Buses and up to nine Chargers - Bus funding provides for a future order of up to 70 40-foot battery-powered, zero-emission, all-electric, fully accessible, public transit buses with en-route charging capabilities. CTA will retire up to 70 1000-Series New Flyer buses that are over 14 years old. Turnkey project to procure Electric buses and associated charging infrastructure.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $23,541,688 $0 $0 $23,541,688

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$71,991,905
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The charging stations were received and installed and reached substantial completion in January 2021. In Q4-2021, seventeen (17) production buses were completed and delivered to CTA. The installation of revenue fare collection systems, communication equipment, network systems were completed in Q2-2022. A total of twenty-three (23) buses were delivered. Nineteen (19) are in service and four are being used at the 74th Garage for operator training. CTA previously exercised an option for an additional twenty-two (22) buses. CTA’s Infrastructure department continued working with Bus Engineering to finalize the budget breakdown and scope for the 103rd Garage. Pre-production activities continued where production is expected to start in June 2025 and delivery of the first vehicle is expected by the end of 2025.

Last Updated 06.10.2024

+ CTA Red/Purple Modernization - Phase 1 Modernization Rail $0 $0 On Schedule

Project Details

Description
North Main Line - RPM The purpose of the Red and Purple Modernization (RPM) Program is to expand capacity to meet growing ridership demand; reduce travel times; improve access to job markets and destinations; better utilize existing transit infrastructure; bring the existing infrastructure to a state of good repair; and improve access to the system for patrons with disabilities. FY2021-2025 funds will continue RPM Phase One funding stream.Red Purple Modernization phase one project consists the following interrelated and concurrent projects, as defined in the environmental documents to be developed by the CTA:RED-PURPLE BYPASS PROJECT. This element would construct a fifth track bypass flyover immediately north of the CTA Belmont Station to separate northbound Brown Line trains that currently conflict with southbound Purple Line trains and both northbound and southbound Red Line trains. This project includes construction of a new fifth track bypass flyover and replacement or renovation of approximately 0.3 mile of associated mainline track.LAWRENCE TO BRYN MAWR MODERNIZATION PROJECT. This modernization project would replace 1.3 miles of the existing rail line from Leland Avenue on the south to approximately Ardmore Avenue on the north. This section of track includes four stations - Lawrence, Argyle, Berwyn, and Bryn Mawr. The project would expand and modernize these four stations. The project would also provide ADA access to transit customers with disabilities in a two-mile stretch of the north Red Line that currently does not have accessible stations.CORRIDOR SIGNAL IMPROVEMENTS. This project would improve the signal system and special trackwork generally between Belmont and Loyola stations. Improvements would occur within CTA's existing right-of-way. The scope of work includes planning, design, procurement, and installation of wayside equipment and special trackwork that are significantly past their useful lives. This project also includes improvements to existing special trackwork.CONTINUED INTERIM CAPITAL IMPROVEMENTS. This project would improve track infrastructure conditions between Belmont Station and Linden Station in order to maintain service along existing rail lines. This work would take place within the CTA's existing right-of-way.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $777,725,323 $0 $0 $777,725,323

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$2,203,408,226
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The Corridor Signal Improvements (CSI) project monitored the track circuit in the LBMM Stage B area and resumed installing brackets and messenger cables along embankment walls north of Thorndale. Additionally, innerduct installation for the communications network backbone continued. The Red Purple Modernization (RPM) project removed the old Clark Relay House, addressed signal testing discrepancies, and prepared for factory tests of new signal equipment. The Jarvis Relay Room began mechanical, electrical, and fire suppression improvements. The Lawrence to Bryn Mawr Modernization (LBMM) completed significant structural work, including embankment excavation, retaining wall removal, and concrete deck pours for the Ardmore transition bridge. Drilling caissons and constructing concrete piers for the elevated structure progressed, and foundational work for the Bryn Mawr station began, alongside steel erection for the platform and escalator/elevator trusses. The

Last Updated 06.10.2024

+ CTA Rehabilitate Blue Line - Kimball Subway Waterproofing Track & Structure Rail $0 $0 On Schedule

Project Details

Description
Subway Waterproofing & Track - Funding will provide for critical waterproofing patchwork needed to continue rail service through the Blue Line O'Hare branch.. Due to funding restrictions CTA cannot move forward with original scope of work to mitigate water infiltration in the Dearborn subway.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,120,513 $0 $0 $4,120,513

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$7,785,710
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Work activities under this project are ongoing. The waterproofing and grout injection work is performed by CTA forces whenever single-track access is available.

Last Updated 06.10.2024

+ CTA Replace Buses - Options to Purchase Up To 500 of 1,030 Rolling Stock Bus $0 $74,570,219 On Schedule

Project Details

Description
The scope of this project will provide for the engineering, purchase, and inspection of fully accessible, air conditioned Clean Diesel buses; including a spare parts inventory. Engineering includes: development of specifications, pre-bid engineering meetings, onsite inspections of prospective bidders and/or their vendors’ plants, inspection of buses during production and acceptance of vehicles after delivery. 5 Year funds will continue funding stream for the Option(s) to replace up to 500 additional buses. Option(s) to the Base (100) contract order consist of up to an additional 500 buses that will initiate multiple orders to replace the 1000 Series New Flyer buses that have been in service since FY 2006.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $50,883,624 $50,883,624
State $0 $0 $23,686,595 $23,686,595
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $325,779,736 $0 $74,570,219 $400,349,955

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$449,623,251
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
As of July 2024, all 300 buses from the base order, Option 1 and Option 2 have been delivered and placed in service. Under Option 3, 90 buses have been delivered. CTA has also exercised Option 4 and 5 for an additional 200 buses. Option 4 has 80 buses built and ready for delivery with the final delivery in March 2025. Option 5 is the final option of this project.

Last Updated 12.19.2024

+ Metra Right of Way Equipment Support Facilities & Equipment Rail $0 $0 On Schedule

Project Details

Description
This project involves the purchase of various pieces of equipment to be utilized by Metra’s Engineering Department. Equipment purchased under this project will include end loaders, track backhoes, hi-rail equipment for track inspection, track tampers, track stabilizers, tie cranes, and other equipment.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $23,897,343 $0 $0 $23,897,343

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$27,694,765
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra has procured and is awaiting delivery of 2 locomotive cranes, 2 hi-rail track excavators, 2 tower trucks and 10 wheel loaders. The track stabilizer, spot temper, blast regulator, tie crane and diesel powered skid-steer loader have been paid for and delivered to Metra.

Last Updated 03.27.2025

+ Metra Shelters Stations & Passenger Facilities Rail $0 $2,240,000 On Schedule

Project Details

Description
This project will fund the installation of shelters at stations across the entire Metra system to provide passengers with climate-controlled waiting space. Multiple project locations will be designed and constructed in bundled packages. Related improvements may be included in the project construction phase such as new pathways, retaining walls, staircases, handrails, accessibility elements, signage, and other minor improvements.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $2,240,000 $2,240,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,128,224 $0 $2,240,000 $9,368,224

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$6,025,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Aluminum shelters continue to be installed throughout the system. Currently, shelter installation is on hold at Morton Grove, Western Ave., 67th St., 83rd St.. Western Avenue and Woodstock had the NEPA review completed and are at 90% design and continuing. Procurement packages for the next package of stations is in process.

Last Updated 03.27.2025

+ Metra Smart Gates Electrical, Signal & Communications Rail $0 $24,000,000 On Schedule

Project Details

Description
This project involves upgrades to protected grade crossings to improve the safety and reliability of grade crossing protections. Metra has approximately 300 active grade crossings with warning devices. This project will fund upgrades of circuitry at these grade crossings to the latest technology. Metra will install monitors to check the condition of the grade crossing protection system. When a monitor detects an anomaly, the system will send a notice to the back office and dispatch a signal maintainer to perform repairs. PTC Wireless crossings are being added to the scope in 2025 and beyond.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $24,000,000 $24,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $20,000,000 $0 $24,000,000 $44,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$13,719,036
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra has executed a contract with a software vendor. Currently, there are 14 locations being updated with remote monitoring. The software vendor is also working on the user interface. The software was developed and is working in a lab environment. The construction and hardware installation at grade crossings is ongoing.

Last Updated 12.19.2024

+ Metra Station Displays (TROI Net) Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
The TROI-Net Station Displays Project is the design and rollout of the next generation of Metra's VIS Signs as they reach the end of their useful life and require replacement. Instead of one VIS Sign per station, TROI-Net Station Displays will be installed at more than one location at most stations. To meet accessibility requirements and like the current VIS Signs, TROI-Net Station Displays will provide the visual part of Metra's Audio/Visual announcements at stations. TROI-Net Station Displays will also provide live train tracking information, customer information messages, and emergency messages to Metra’s customers.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $13,536,320 $0 $0 $13,536,320

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$9,600,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Displays have begun being delivered in this reporting period but delivery of brackets are still waiting for delivery. Installation has begun and 32 stations have been completed with 64 monitors installed.

Last Updated 06.10.2024

+ Metra Stoney Creek Bridge- SWS Track & Structure Rail $0 $0 Behind Schedule

Project Details

Description
This project funds engineering design services for the replacement of the Stoney Creek Bridge on Metra’s SouthWest Service. The bridge, constructed in 1917, spans over Stoney Creek in Oak Lawn at milepost 16.3. Construction funds are provided in future years.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $18,230,000 $0 $0 $18,230,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$12,400,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The 90% design has been completed and approved by Metra. The design is advancing to the 100% design submittal. The permit process activities are in progress.

Last Updated 12.19.2024

+ Metra Ticket Vending Machines Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
This project is the first phase of installing up to 310 ticket vending machines (TVMs) at selected stations throughout the Metra system to provide added amenities to Metra customers. The TVMs will offer a variety of ticket purchasing options and make purchasing tickets faster, easier, and more convenient for our customers. The TVMs will be fully ADA-accessible and will offer the ability to purchase tickets using contactless cards and mobile wallet applications and will no longer need to insert debit/credit cards into the machine.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $38,160,000 $0 $0 $38,160,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$46,000,090
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project is currently in the production phase. The manufacturing of ticket vending machines continued during this reporting period. One hundred and thirty-four (134) total TVM’s have been delivered and installed. The extended pilot program continues with the newly installed TVM’s.

Last Updated 03.27.2025