Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the December 2024 Project Management Oversight report. 

i

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Project Title Asset Category Mode 2025 Funding 2025-2029 Funding Status
+ Metra Ties & Ballast MED Track & Structure Rail $0 $0 On Schedule

Project Details

Description
These projects consist of the replacement of cross ties, switch ties and ballast. In order to maintain proper track gauge and surface, it is necessary to replace ties and ballast periodically. This improves the riding quality of the trains and reduces the incidence of slow orders, which adversely affect adherence to train schedules. These projects represent part of an ongoing program to replace ties and ballast throughout the commuter territory.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $13,446,000 $0 $0 $13,446,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$4,100,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Major elements for this project included ironworkers; track, signal and utilities work. Track and structure improvements were completed during this reporting period and final invoices remain. This will be the final update on this project.

Last Updated 04.01.2024

+ Metra Ties & Ballast RID Track & Structure Rail $0 $0 On Schedule

Project Details

Description
These projects consist of the replacement of cross ties, switch ties and ballast. In order to maintain proper track gauge and surface, it is necessary to replace ties and ballast periodically. This improves the riding quality of the trains and reduces the incidence of slow orders, which adversely affect adherence to train schedules. These projects represent part of an ongoing program to replace ties and ballast throughout the Rock Island District.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,520,000 $0 $0 $7,520,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,920,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Major elements for this project includes ironworkers; track, signal and utilities work. Track and structure improvements completed during this reporting period. This will be the final update on this project.

Last Updated 06.10.2024

+ Pace Transit Signal Priority (TSP) Electrical, Signal & Communications Bus $0 $0 On Schedule

Project Details

Description
Transit Signal Priority Integration - TSP implementation along priority corridors as part of the Regional Transit Signal Priority Implementation Program. Pace plans to deploy TSP along nine additional corridors at approximately 300 signalized intersections. The corridors include: 159th Street, Sibley Boulevard/147th Street, Roosevelt Road, Cicero Avenue, 95th Street, Grand Avenue (Lake County), Cermak Road, I-90 Transit Corridor Access Intersections and Halsted Street. This form represents the portion of the project funded with PAYGO in 2024. Years 2021-2023 of TSP related projects are funded with ICE funds as shown in Exhibit I.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $8,336,578 $0 $0 $8,336,578

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$14,031,402
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The vendor received the permit to implement TSP system along 58 signalized intersections of Dempster Street from IDOT. TSP data and operations monitoring continued on Dempster Avenue, testing and TST data analysis continued on Grand Ave. as well as Roosevelt Road. TSP deployment was completed at 147th Street and 95th Street where the vendor continues testing. Cicero Ave. has TSP installation ongoing. The contractor is working on permit acquisitions for Cermak, Rand Road, and 159th.

Last Updated 06.10.2024

+ Metra UP North Line - North 11 Bridges and Ravenswood Station Track & Structure Rail $0 $0 Behind Schedule

Project Details

Description
This project involves the replacement of 22 bridges on the UP North Line in Chicago, Illinois. The structural scope of work will include, but not be limited to, replacement of existing stone abutments, retaining wall construction, steel spans, and decks. Also, some track work will be accomplished between the bridges, including the replacement of wood ties with concrete ties, and some commuter station modifications will be required, including the Ravenswood Station. To ensure reliable train operations, theproject will include various signal improvements, including: new interlockers at Addison Street (MP 5.0) and Rosehill (MP 7.3, between Balmoral Avenue and Bryn Mawr Avenue), and upgrades to the Deering interlocker (MP 3.2). In
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,776,054 $0 $0 $1,776,054

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$50,255,463
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The bridge construction has been completed in September 2021. The station contractor reached substantial completion in August 2023. The contractor continues to address punch list items on the station. The station had a soft opening at the beginning of August and its opening ceremony at the beginning of October. This will be the final update of this project.

Last Updated 12.14.2023

+ Metra Van Buren St. Station Stations & Passenger Facilities Rail $0 $24,485,250 On Schedule

Project Details

Description
A complete renovation of the downtown Chicago terminal station will rehabilitate the existing historic waiting rooms, replace the roof assembly while maintaining the green roof, and will replace the pedestrian tunnel in the park. A new 'pop-up' entrance in Grant Park will add a new access stair case and elevator and add an ADA-compliant ramp connecting to the pedestrian bridge. The pedestrian tunnel under Michigan Ave will be waterproofed and a new elevator will be added to the Jackson Blvd platform. The scope of work includes rehabilitation of the stair enclosures and elevator west of Michigan Avenue, replacement of the platforms, new full-length platform canopies, heated warming shelters, construction of a new vendor space at lower level, and all new mechanical, electrical, and plumbing throughout the station.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $24,485,250 $24,485,250
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $24,485,250 $24,485,250

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$48,126,300
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra awarded the consultant contract for station concept design. The concept design is at 15% completion and on hold pending completion of lakefront ordinance protection, NEPA, and environmental processes. Documents are being prepared to be submitted for lakefront ordinance for approval. Environmental and NEPA work is ongoing. The Memorandum of Understanding was completed during this reporting period. There was a solicitation for a new LIQ blanket for design services to get the design from 10% to 30% and then a separate solicitation from 30% to 100%. The design is expected to be completed in the beginning of 2027.

Last Updated 03.27.2025