Regional Capital Program

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects are updated on an annual basis. This page shows details about the funding for each priority project.

The 2025-2029 5-Year Regional Capital Program includes over 250 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2025-2029 Regional Capital Program. Beginning with the 2025-2029 Capital Program, projects are evaluated based on 15 measures which were identified in the new Regional Transit Strategic Plan, Transit is the Answer. All projects in the 2025-2029 program show the detailed evaluations in this site.

The metrics include evaluations of Equity and Accessibility which are used in the performance-based allocation process. The region has committed to dedicating 20% of programmed funds to projects that fulfill the regional goals of improving equity and accessibility for 2025 and beyond as a part of the new performance-based capital allocation process

The Service Boards have met and exceeded the 20% goal for the 2025-2029 budget years.

Detailed analysis of the capital evaluation metrics is included in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

Toggle Agency Priority Project Mode 2025 Funding 2025-2029 Funding 10 Year Funding Needed 10 Year Unfunded Need
+ Metra Uncategorized Projects - Metra Rail $6,740,000 $42,220,000 $0 $-42,220,000

These are a miscellaneous set of Capital projects undertaken by Metra.

Toggle Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ COVID 19 - Modifications N/A Rail $0 $0

Project Details

Description
This project will fund modifications to gallery cars and EMU's to improve the interior air quality and sanitation within Metra's railcar fleet. Project activities will address public health concerns and to mitigate airborne viruses. Improvements to be made by this project may include, but is not limited to improving HVAC system components, filter upgrades, new UV lights, installation of hand sanitizer dispensers, signage, and other upgrades as needed.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $8,450,000 $0 $0 $8,450,000

Last Updated 12.16.2022

+ Cybersecurity Systems N/A Rail $400,000 $1,600,000 ✔︎

Project Details

Description
This project covers all cybersecurity-related hardware, software, professional services, and cloud investments for the entire agency. The project also includes the purchase of hardware and software for multiple networks and segments including IT systems, positive train control (PTC), SCADA infrastructure, signal, telecom, and camera networks. The purchased equipment will cover vulnerability scanning and prioritization, patch automation and remediation, Security Information and Event Management (SIEM), and endpoint detection and response (EDR).This project will fund the purchase and installation of equipment and software for scanning, prioritization, and remediation of vulnerabilities. This also includes the purchase of hardware and software for multiple networks and segments including IT systems, positive train control (PTC), SCADA infrastructure, and signal, telecom, and camera networks. The purchased equipment will cover vulnerability scanning and prioritization, patch automation and remediation, Security Information and Event Management (SIEM), and endpoint detection and response (EDR).
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $400,000 $1,200,000 $1,600,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,200,000 $400,000 $1,200,000 $2,800,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,246,742
On Budget
Ahead of Schedul

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Contracts for cybersecurity and vulnerability software were awarded and software installation completed for 13 contracts. Contracts were awarded for vulnerability assessment. Software implementation was completed during this reporting period. This will be the final update on this project.

Last Updated 06.10.2025

+ Infrastructure Engineering BNS N/A Rail $0 $0

Project Details

Description
This project funds various engineering responsibilities for capital projects. Metra’s Engineering Department as well as consultant engineers provide support to capital projects. The associated professional consultant services include design engineering and/or construction management in the areas of civil, structural, electrical, mechanical, signal, communications and environmental engineering. Work will be done on the BNSF.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $900,000 $0 $0 $900,000

Last Updated 12.16.2022

+ Infrastructure Engineering MED N/A Rail $0 $0

Project Details

Description
This project funds various engineering responsibilities for capital projects. Metra’s Engineering Department as well as consultant engineers provide support to capital projects. The associated professional consultant services include design engineering and/or construction management in the areas of civil, structural, electrical, mechanical, signal, communications and environmental engineering. Work will be done on the Metra Electirc District.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $900,000 $0 $0 $900,000

Last Updated 12.16.2022

+ Infrastructure Engineering MET N/A Rail $5,000,000 $37,830,000

Project Details

Description
This project funds various engineering responsibilities for capital projects. Metra’s Engineering Department as well as consultant engineers provide support to capital projects. The associated professional consultant services include design engineering and/or construction management in the areas of civil, structural, electrical, mechanical, signal, communications and environmental engineering. Work will be done systemwide.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $5,000,000 $32,830,000 $37,830,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $6,700,000 $5,000,000 $32,830,000 $44,530,000

Last Updated 12.19.2024

+ Infrastructure Engineering MWD N/A Rail $0 $0

Project Details

Description
This project funds various engineering responsibilities for capital projects. Metra’s Engineering Department as well as consultant engineers provide support to capital projects. The associated professional consultant services include design engineering and/or construction management in the areas of civil, structural, electrical, mechanical, signal, communications and environmental engineering. Work will be done on the Milwaukee District.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $900,000 $0 $0 $900,000

Last Updated 12.16.2022

+ Infrastructure Engineering RID N/A Rail $0 $0

Project Details

Description
This project funds various engineering responsibilities for capital projects. Metra’s Engineering Department as well as consultant engineers provide support to capital projects. The associated professional consultant services include design engineering and/or construction management in the areas of civil, structural, electrical, mechanical, signal, communications and environmental engineering. Work will be donw on the URock Island District.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $900,000 $0 $0 $900,000

Last Updated 12.16.2022

+ Infrastructure Engineering UPR N/A Rail $0 $0

Project Details

Description
This project funds various engineering responsibilities for capital projects. Metra’s Engineering Department as well as consultant engineers provide support to capital projects. The associated professional consultant services include design engineering and/or construction management in the areas of civil, structural, electrical, mechanical, signal, communications and environmental engineering. Work will be done on the Union Pacific Railroad.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $900,000 $0 $0 $900,000

Last Updated 12.16.2022

+ IT Components & Services N/A Rail $0 $900,000 ✔︎

Project Details

Description
This project includes the procurement and installation components to support Metra’s technology and computer systems. The project may include but is not limited to the physical hardware, virtualization software, storage area networks, firewalls, switches, communications hardware, cloud connectivity software and services, and circuits for the data center at Metra Headquarters. The current components are at the end of their useful life or are technically obsolete.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $900,000 $900,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,073,000 $0 $900,000 $7,973,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$12,059,193
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This is a multiple year and multiple project type of capital project. Purchase orders have been awarded for various computer hardware and software. Hardware has been delivered and installed. Purchase Order Releases for computer hardware and software continue in process and deliveries will continue over the next several years.

Last Updated 06.10.2025

+ Systemwide Cameras N/A Rail $1,340,000 $1,890,000 ✔︎

Project Details

Description
This project consists of adding up to 600 cameras per year throughout the Metra system. Installation on the Rock Island (RI) Line and the Southwest Service (SWS) Line, this project may support up to 1,300 cameras to be installed at all grade crossings and the 23 existing depots on the RI and SWS. Project expenses may including, but are not limited to, cameras and associated wiring and masts. This is a multi-year, phase-funded project.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $1,340,000 $550,000 $1,890,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,450,000 $1,340,000 $550,000 $6,340,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$2,450,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Camera licenses, security cameras, SD cards, and accessories were purchased, and installation completed. IP cameras and equipment purchases are currently underway and are 26% complete.

Last Updated 06.10.2025

+ CTA Maintenance Facilities Rehabilitation System $6,012,402 $40,339,405 $200,000,000 $159,660,595

Perform facilities maintenance activities to keep the fleet in a state of good repair.

Toggle Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ 2020 - Facilities Maintenance - Systemwide Support Facilities & Equipment System $0 $0 ✔︎

Project Details

Description
Funding will be targeted at preventive maintenance projects at various CTA facilities systemwide. These projects will improve CTA's capacity to maintain stations and improve customer comfort and safety. CTA's Facilities department will identify stations for this targeted preventive maintenance work, driven by regular field audits performed by maintenance staff. Projects currently anticipated for this funding source may include leak remediation and grouting in stations; rehabilitation of CTA elevators and escalators (ADA); ceiling, roof or canopy repair / patching; lighting upgrades; painting and signage, among other items. This work will be performed by CTA maintenance forces with material procured as part of this project. Work will be conducted throughout the system and is considered routine preventive maintenance.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $20,000,000 $0 $0 $20,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$12,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Facilities improvements is part of an ongoing program. The preventive maintenance reduces the occurrences of defects which occur as a result of water/snow, human error, leaks, asset wear and tear, and bearing failures. This particular part of the program is completed. This will be the final update on this project.

Last Updated 07.10.2022

+ 2021 - Facilities Maintenance - Systemwide Support Facilities & Equipment System $0 $0 ✔︎

Project Details

Description
Funding will be targeted at preventive maintenance projects at various CTA facilities systemwide. These projects will improve CTA's capacity to maintain stations and improve customer comfort and safety. CTA's Facilities department will identify stations for this targeted preventive maintenance work, driven by regular field audits performed by maintenance staff. Projects currently anticipated for this funding source may include leak remediation and grouting in stations; rehabilitation of CTA elevators and escalators (ADA); ceiling, roof or canopy repair / patching; lighting upgrades; painting and signage, among other items. This work will be performed by CTA maintenance forces with material procured as part of this project. Work will be conducted throughout the system and is considered routine preventive maintenance.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $20,000,000 $0 $0 $20,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$20,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The preventive maintenance reduces the occurrences of defects which occur as a result of water/snow, human error, leaks, asset wear and tear, and bearing failures. Facilities improvements were completed during this reporting period. This will be the final update on this project.

Last Updated 04.01.2024

+ 2022 - Facilities Maintenance - Systemwide Support Facilities & Equipment System $0 $0 ✔︎

Project Details

Description
Funding will be targeted at preventive maintenance projects at various CTA facilities systemwide. These projects will improve CTA's capacity to maintain stations and improve customer comfort and safety. CTA's Facilities department will identify stations for this targeted preventive maintenance work, driven by regular field audits performed by maintenance staff. Projects currently anticipated for this funding source may include leak remediation and grouting in stations; rehabilitation of CTA elevators and escalators (ADA); ceiling, roof or canopy repair / patching; lighting upgrades; painting and signage, among other items. This work will be performed by CTA maintenance forces with material procured as part of this project. Work will be conducted throughout the system and is considered routine preventive maintenance.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $12,000,000 $0 $0 $12,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$12,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The preventive maintenance reduces the occurrences of defects which occur as a result of water/snow, human error, leaks, asset wear and tear, and bearing failures. Facilities improvements were completed this reporting period and final invoices remain. This will be the final update on this project.

Last Updated 04.01.2024

+ 2023 - Facilities Maintenance - Systemwide Support Facilities & Equipment System $0 $0 ✔︎

Project Details

Description
Maintenance Facilities Rehabilitation: Funding will be targeted at preventive maintenance projects at various CTA facilities systemwide. These projects will improve CTA's capacity to maintain stations and improve customer comfort and safety. CTA's Facilities department will identify stations for this targeted preventive maintenance work, driven by regular field audits performed by maintenance staff. Projects currently anticipated for this funding source may include leak remediation and grouting in stations; rehabilitation of CTA elevators and escalators (ADA); ceiling, roof or canopy repair / patching; lighting upgrades; painting and signage, among other items. This work will be performed by CTA maintenance forces with material procured as part of this project. Work will be conducted throughout the system and is considered routine preventive maintenance.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $12,000,000 $0 $0 $12,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$12,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Preventive maintenance reduces the occurrences of defects which occur as a result of water/snow, human error, leaks, asset wear and tear, and bearing failures. Facilities improvements were ongoing during this reporting period and maintenance work continues.

Last Updated 06.10.2025

+ 2024 Facilities Maintenance - Systemwide Support Facilities & Equipment System $0 $0

Project Details

Description
Funding will be targeted at preventive maintenance projects at various CTA facilities systemwide. These projects will improve CTA's capacity to maintain stations and improve customer comfort and safety. CTA's Facilities department will identify stations for this targeted preventive maintenance work, driven by regular field audits performed by maintenance staff. Projects currently anticipated for this funding source may include leak remediation and grouting in stations; rehabilitation of CTA elevators and escalators (ADA); ceiling, roof or canopy repair / patching; lighting upgrades; painting and signage, among other items. This work will be performed by CTA maintenance forces with material procured as part of this project. Work will be conducted throughout the system and is considered routine preventive maintenance.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,030,281 $0 $0 $3,030,281

Last Updated 12.14.2023

+ 2025 - Facilities Maintenance - Systemwide Support Facilities & Equipment System $3,030,281 $15,151,405

Project Details

Description
Funding will be targeted at preventive maintenance projects at various CTA facilities systemwide. These projects will improve CTA's capacity to maintain stations and improve customer comfort and safety. CTA's Facilities department will identify stations for this targeted preventive maintenance work, driven by regular field audits performed by maintenance staff. Projects currently anticipated for this funding source may include leak remediation and grouting in stations; rehabilitation of CTA elevators and escalators (ADA); ceiling, roof or canopy repair / patching; lighting upgrades; painting and signage, among other items. This work will be performed by CTA maintenance forces with material procured as part of this project. Work will be conducted throughout the system and is considered routine preventive maintenance.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $3,030,281 $12,121,124 $15,151,405
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $3,030,281 $12,121,124 $15,151,405

Last Updated 12.19.2024

+ Boiler Replacement (Rosemont) Support Facilities & Equipment System $979,000 $979,000

Project Details

Description
Funding will be targeted to boilers at Rosemont Rail Facility that are approximately 40 years old and are beyond their useful life.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $979,000 $0 $979,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $979,000 $0 $979,000

Last Updated 12.19.2024

+ Building Envelope Repairs and MEP Upgrades Systemwide Support Facilities & Equipment System $0 $17,200,000

Project Details

Description
Funding will be targeted to addressing a large backlog of building improvements needed to bring CTA’s station, bus, and rail facilities into a state of good repair, including building envelope repairs and mechanical, electrical, and plumbing (MEP) upgrades. Building envelope repairs at bus and rail facilities are targeted to building facades that are in a state of disrepair, causing water infiltration that will worsen over time and ultimately cause more significant damage, as well as worker safety issues.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $17,200,000 $17,200,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $17,200,000 $17,200,000

Last Updated 12.19.2024

+ Building Envelope Repairs Skokie Substation Support Facilities & Equipment System $0 $1,130,000

Project Details

Description
Funding will be targeted to addressing the building facade that is in a state of disrepair, causing water infiltration that will worsen over time and ultimately cause more significant damage, as well as worker safety issues. Specific building envelope repair needs include tuckpointing, sealant replacement, window and door replacement, and concrete repairs.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $1,130,000 $1,130,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $1,130,000 $1,130,000

Last Updated 12.19.2024

+ Facilities Critical Needs- Substation Roof Repairs - Phase II Support Facilities & Equipment Rail $0 $0 ✔︎

Project Details

Description
Program would address the most immediate critical needs at CTA facilities systemwide to enable their safe and reliable operation. The goal would be to have an annual appropriation in the CIP that would be solely dedicated toward addressing this Program. Transit service safety and reliability is affected by out-of-date rail, bus, and maintenance facilities.The project will complete roof replacements at five CTA substations: Calvary, Lotus, Des Plaines, Ashland, and O’Hare. The project will also complete exterior façade repair at the O’Hare Substation, including wall panel and louver replacement, masonry wall and expansion joint repairs, painting, doors, and new surface mounted exterior light fixtures. Design will be completed in-house by CTA engineering staff.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,628,767 $0 $0 $3,628,767

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$4,389,335
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Construction has been completed. The roof replacements at seven substations have been completed as well as repairs to the building envelope at O’Hare substation. This project is currently in the close out phase. This is the last report on this project.

Last Updated 06.10.2024

+ PowerHouse Mechanical Upgrades Support Facilities & Equipment System $939,000 $939,000

Project Details

Description
Funding will be targeted to mechanical upgrades to support the existing four boiler systems which are approaching 70 years old.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $939,000 $0 $939,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $939,000 $0 $939,000

Last Updated 12.19.2024

+ Substation Roof Repairs - Phase III Support Facilities & Equipment Rail $1,064,121 $4,940,000 ✔︎

Project Details

Description
Funding will be targeted to replace substation roofs that are worn, damaged, and beyond their life expectancies. Locations include Skokie, Douglas, Kolmar, Archer, Edmunds, Gage, Pershing, and Springfield substations.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $1,064,121 $3,875,879 $4,940,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $1,064,121 $3,875,879 $4,940,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$4,389,335
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Construction has been completed. The roof replacements at seven substations have been completed as well as repairs to the building envelope at O’Hare substation. This project is currently in the close out phase. This is the last report on this project.

Last Updated 12.19.2024

+ CTA Subway Life Safety Improvements Rail $5,250,000 $18,000,000 $604,309,000 $586,309,000

Upgrade to existing subway ventilation equipment.

Toggle Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ Subway Life Safety Track & Structure Rail $5,250,000 $18,000,000

Project Details

Description
This project improves safety across CTA Right of Way (ROW), particularly in the subway systems and facilities to help meet life safety requirements per applicable codes. The project will complete assessments and the design approaches for safety issues in the subway. Items to investigate include, but are not limited to:• Ventilation improvements• Vent shaft grate replacements• Subway pumps and controls rehabilitation• Subway emergency egress footwalks• LED lighting improvements• Emergency Light Feed (ELF) upgrades• Subway sewer restoration
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $5,250,000 $12,750,000 $18,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,000,000 $5,250,000 $12,750,000 $21,000,000

Last Updated 12.19.2024

+ Subway Underground Underwater Emergency Exit Track & Structure Rail $0 $0

Project Details

Description
The vision for this project is to secure CTA’s underground and underwater tunnel subway system and emergency exits by leveraging technology to fill the security deficiencies in the physical tunnel infrastructure that otherwise would be prohibitively expensive and improbable to achieve with humans. The goal is to create a comprehensive yet sustainable solution that ultimately prevents, detects, tracks, authorizes, and responds to all human activity in the restricted, non-public areas of the tunnels.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,829,838 $0 $0 $3,829,838

Last Updated 12.19.2024

+ Metra Rock Island Intercity Improvements (RI3) Rail $4,000,000 $4,000,000 $1,019,812,500 $1,015,812,500

Infrastructure improvements to support enhance service, additional capacity, rerouting the SWS and Amtrak trains bound for St. Louis and Texas.

Toggle Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ Rock Island Connection and 3rd track Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Establish a new 3rd main on the Rock Island Line. The project study limits shall be from MP 0.0 (LaSalle Station) to MP 10.5 (Gresham Jct.). The new 3rd main is anticipated to extend from the new 16th Interlocking at MP 1.0 presently in design to the new CREATE P2 Interlocking at CP 74th. It is also anticpated that a new crossover will be required at Gresham to faciliate train movement into and out of the new 3rd main.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $11,300,000 $0 $0 $11,300,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$14,628,564
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The preliminary engineering for this project has started. The NEPA Scopeof- Work (SOW) was advertised in October 2022. Survey work started in the first week of October 2022 and NEPA activities continue progressing.

Last Updated 06.10.2025

+ Rock Island Intercity Improvements (RI3) Track & Structure Rail $4,000,000 $4,000,000

Project Details

Description
This project will establish a new 3rd main line track on the Rock Island (RI) Line and various improvements between the LaSalle Street and Joliet terminals. The new 3rd main line track is anticipated to extend from the new 16th Interlocking at MP 1.0 to the new CREATE P2 Interlocking at CP 74th. The project may include but is not limited to new crossovers, the rehabilitation of bridges, reconstruction of retaining walls, modifications to existing stations, and other improvements to facilitate train movements onto the new 3rd main line track. This project may also include the extension of the 49th Street Yard, new yard facilities, and other improvements to increase the capacity of operations at the 49th Street Yard. Additional improvements include signaling and grade crossing improvements from Gresham to Joliet as well as an improved Joliet station platform for Metra and Amtrak use.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $4,000,000 $0 $4,000,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $4,000,000 $0 $4,000,000

Last Updated 12.19.2024

+ CTA Bus Turnarounds Bus $3,344,922 $59,925,000 $72,425,000 $12,500,000

The proposed work will range from reconstructing existing terminals to construction of a new terminal in a new location. Planning will further evaluate the terminal and bus turnaround identified and prioritize the top three locations to be constructed/reconstructed within this five-year period.
.

Toggle Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ Bus Turnaround ADA & Site Improvements- Halsted and 79th Street Stations & Passenger Facilities Bus $3,344,922 $7,900,000

Project Details

Description
This funding will provide for an ADA accessible bus turnaround. Work includes reconstruction of the concrete island platform with ADA ramps, guardrails, and required barriers; addition of an accessible sidewalk path to the island platform crosswalk; complete reconstruction of the bus turnaround and associated pavement, including new ADA curb ramps; new signage, LED lighting, cameras, passenger windbreaks, and landscaping; upgraded toilet facilities for accessibility with new utility connections; and addition of public art Addition of push button for audio for next bus/train schedule, tactile path, tactile signage, heat lamps and LED lights.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $3,344,922 $4,555,078 $7,900,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $3,344,922 $4,555,078 $7,900,000

Last Updated 12.19.2024

+ Bus Turnaround Improvements - Employee Restrooms Stations & Passenger Facilities Bus $0 $25,725,000

Project Details

Description
This funding will provide for permanent restroom facilities at bus turnarounds where they do not exist to improve bus operator well-being. Currently portable toilet services are provided at several locations throughout the system via lease agreements entered into with various third parties. These portable toilets are inadequate and do not meet CTA personnel needs.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $25,725,000 $25,725,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $25,725,000 $25,725,000

Last Updated 12.19.2024

+ Bus Turnaround Improvements - Priority Locations Stations & Passenger Facilities Bus $0 $26,300,000

Project Details

Description
This funding will provide for the reconstruction of bus turnarounds at existing terminals and construction of a new terminal in a new location. . In some cases, such as the location at 31st/Central Park, land acquisition would be necessary to construct a new terminal facility for buses that are currently taking recovery on city streets. Potential locations for improvements or new installations include: 31st/Central Park; Central/Roosevelt; 24th Place/Cicero; 31st/Komensky; Irving Park/Cumberland; Archer/Cicero; 91st/Commercial; Kedzie/Chicago; 75th/Kostner; 35th/Cottage Grove; Western / 79th; 112th / Torrence
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $26,300,000 $26,300,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $26,300,000 $26,300,000

Last Updated 12.19.2024

+ Metra Chicago Union Station Improvements Rail $2,500,000 $8,878,000 $576,108,750 $567,230,750

Implementation of key projects benefiting commuters using Chicago Union Station.

Toggle Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ Chicago Union Station Stations & Passenger Facilities Rail $2,500,000 $2,500,000 ✔︎

Project Details

Description
This project will support the Amtrak-led effort to complete the Final Design phase work and the eventual construction phase to reconstruct the Chicago Union Station (CUS) Concourse. Metra and Amtrak collaborate to maintain and improve CUS and the facilities within the terminal. Project funds will provide Metra’s local matching funding commitment to Amtrak’s project.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $2,500,000 $0 $2,500,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,000,000 $2,500,000 $0 $5,500,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$2,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The project is in preliminary engineering and working towards the 30% design milestone and the NEPA process is ongoing. Design activities continued during this reporting period.

Last Updated 06.10.2025

+ Chicago Union Station Interlockers Stations & Passenger Facilities Rail $0 $0 ✔︎

Project Details

Description
This project involves the modernization and upgrading of outmoded interlockings at the north and south ends of Chicago Union Station (CUS). The project will include, but not be limited to, new rail, ties, ballast cleaning or replacement, upgrades to signal infrastructure, replacement of switches and components, and other related work as needed. Amtrak contributes funds towards a portion of the project work.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $13,000,000 $0 $0 $13,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$13,096,850
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Amtrak identified the scope of work for 2025 activities and being reviewed with Metra. This will be added in the Facility Agreement with Metra to complete the project. The project continues with Amtrak replacing and upgrading switches, signals and rails at Harrison St and Taylor St on the north and south ends of CUS.

Last Updated 06.10.2025

+ Crew Facilities Chicago Union Station Stations & Passenger Facilities Rail $0 $6,378,000

Project Details

Description
Remodeling of the Chicago Union Station Crew Facility will provide adequate female staff locker, shower, toilet, and bunk facilities. The remodel will also upgrade the male staff locker, shower, toilet, and bunk facilities. The remodel will also revise the mechanical systems to provide the required ventilation, which has been an issue in the facility. Finally, the remodel will improve lighting in the facilities and confirm life safety systems meet the applicable building codes.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $700,000 $700,000
State $0 $0 $5,678,000 $5,678,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $6,378,000 $6,378,000

Last Updated 12.19.2024

+ Pace Paratransit Vehicles - Replacement Bus $2,284,531 $40,714,447 $84,480,000 $43,765,553

Replacement of vehicles reaching useful life.

Toggle Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ Electric Paratransit Vehicles Rolling Stock Bus $0 $0

Project Details

Description
This project will fund the purchase of electric paratransit vehicles.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,000,000 $0 $0 $2,000,000

Last Updated 06.22.2023

+ Purchase 15-passenger Paratransit Vehicles Rolling Stock Bus $2,284,531 $40,714,447 ✔︎

Project Details

Description
Paratransit Vehicles - Pace plans to purchase replacement vehicles (22'-25' cutaway) including associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections) for paratransit services.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $2,284,531 $22,459,916 $24,744,447
State $0 $0 $15,970,000 $15,970,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $13,013,022 $2,284,531 $38,429,916 $53,727,469

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$69,991,388
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
These buses will service DuPage, Kane, Lake, Will and Cook counties. Pace awarded a new contract in November 2020. The first order was for a quantity of 210 paratransit buses. The final vehicle of the base order was delivered in March 2024. Pace executed a second order of 125 additional vehicles. These vehicles will combine additional paratransit vehicles & vehicles to be used for the community vehicle program. Pace received seven of these 125 vehicles and expects final delivery by the end of 2025.

Last Updated 06.10.2025

+ CTA Non-Revenue Vehicle Replacement Program System $1,225,000 $3,986,025 $63,215,422 $59,229,397

Replacement of vehicles needed for maintenance and operations support.

Toggle Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ Equipment and Non-Revenue Vehicles Program Support Facilities & Equipment System $0 $2,761,025

Project Details

Description
CTA plans to invest funds annually to fund the phased replacement of aged equipment and vehicles used by CTA maintenance groups that include Bus, Rail, Power & Way, and Facilities.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $2,761,025 $2,761,025
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,269,359 $0 $2,761,025 $6,030,384

Last Updated 12.19.2024

+ Non-Revenue Utility Vehicle Replacement Support Facilities & Equipment System $1,225,000 $1,225,000

Project Details

Description
Creates a small, multi-year program to replace, renew, or lease vehicles assigned to the Utility Group with CTA Facility Maintenance. These vehicles are used to provide essential functions for maintaining safe and continuous operation of CTA rail and bus operations. Additional funding will be necessary to fund the full plan.These vehicles include trucks, vans, truck-mounted machinery, snowplows, mobile workspaces, and transport vehicles for other equipment, personnel, and supplies.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $1,225,000 $0 $1,225,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,675,000 $1,225,000 $0 $4,900,000

Last Updated 12.19.2024

+ Non-Revenue Vehicles - Diesel Locomotives Support Facilities & Equipment Rail $0 $0 ✔︎

Project Details

Description
Equipment and Non-Revenue Vehicles (Diesel Locomotives): Funding will provide for the replacement of CTA's diesel locomotive snow fighters. The self-propelled locomotives with special attachments to remove snow and ice during severe winter weather conditions are able to operate and clear system track, so that CTA can safely power up the system to restore/provide service. When traction power is down, this equipment will also be used to move rolling stock to secure locations.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,806,260 $0 $0 $7,806,260

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$22,731,013
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The project is in full production mode. CTA continues to work with the vendor to address final configuration and modifications on the first vehicle before testing on rail and final acceptance. All changes will be pushed to the remaining three locomotives. Delivery of the second vehicle will take place after acceptance of vehicle #1 and the contractor will continue commissioning and delivering of the vehicles.

Last Updated 06.10.2025

+ Security Police Sedans Support Facilities & Equipment Rail $0 $0

Project Details

Description
Replace 32 overaged transit security police sedans.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,300,000 $0 $0 $2,300,000

Last Updated 09.25.2024

+ Metra PTC - systemwide Rail $1,090,860 $7,215,860 $78,000,000 $70,784,140

Install federally-mandated rail operational safety system

Toggle Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ PTC Program Management Electrical, Signal & Communications Rail $0 $0

Project Details

Description
This project will be to facilitate a vendor who can provide Program Management of the entire PTC system and ongoing projects. These projects include, Next Generation Office, CTC over ITCM, ITCM support, PTC Data Distallation Tool, Wabtec Master Service Agreement, and PTC Hardware Renewal. The scope of this work will also include document control, TPCQMP compliance, and movement of all PTC documentation to ProjectWise. The scope also includes FTA, RTA and IDOT monthly PTC progress reporting.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,000,000 $0 $0 $1,000,000

Last Updated 06.22.2023

+ PTC Renewal (Engineering) Electrical, Signal & Communications Rail $590,860 $4,715,860 ✔︎

Project Details

Description
This project will fund the second phase of the Positive Train Control (PTC) Project. Project funds will update back-office equipment, components, hardware, software, and other equipment that is necessary to maintain safe and consistent operations of Metra’s interoperable PTC system. This project will fund the purchase, installation, and training of a modern, streamlined PTC system to replace the current PTC back office before the end of its useful life. This new system will have an advanced user interface that will provide operational self-checks and will enable safer operations.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $590,860 $4,125,000 $4,715,860
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,690,000 $590,860 $4,125,000 $12,405,860

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,750,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra continued with installations of the software and hardware units for cars and locomotives during this reporting period. Currently, Metra is processing approximately 30 PTC units per month and completed 419 units. Metra will continue installation and upgrading electronic equipment.

Last Updated 06.10.2025

+ PTC- Renewal (Mechanical) Electrical, Signal & Communications Rail $500,000 $2,500,000

Project Details

Description
This project will fund the second phase of Positive Train Control (PTC). Project funds will update onboard equipment and parts in locomotives and cab cars that communicate with the guideway PTC system.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $500,000 $2,000,000 $2,500,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $8,600,000 $500,000 $2,000,000 $11,100,000

Last Updated 12.19.2024

+ Pace Uncategorized Projects - Pace Bus $1,000,000 $1,000,000 $1,000,000 $0

These are a miscellaneous set of Capital projects undertaken by Pace.

Toggle Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ Transit Asset Management N/A Bus $0 $0

Project Details

Description
Transit Asset Management - Consulting services for TAM Plan updates, including condition assessments of Pace facilities.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $400,000 $0 $0 $400,000

Last Updated 12.16.2022

+ Unanticipated Capital N/A Bus $1,000,000 $1,000,000

Project Details

Description
Contingency funding for existing projects or small new projects
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $1,000,000 $0 $1,000,000
Total $3,250,000 $1,000,000 $0 $4,250,000

Last Updated 12.19.2024

+ Vision Plan Implementation Study N/A Bus $0 $0

Project Details

Description
Vision Plan Implementation Study - Consulting services to include a system-wide market analysis and proposed service restructuring plan that will address the goals and objectives of Pace’s Driving Innovation Strategic Vision Plan.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,000,000 $0 $0 $4,000,000

Last Updated 12.16.2022