Regional Capital Program

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects are updated on an annual basis. This page shows details about the funding for each priority project.

The 2024-2028 5-Year Regional Capital Program includes over 250 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2024-2028 Regional Capital Program. Beginning with the 2024-2028 Capital Program, projects are evaluated based on 15 measures which were identified in the new Regional Transit Strategic Plan, Transit is the Answer. All projects in the 2024-2028 program show the detailed evaluations in this site.

The metrics include evaluations of Equity and Accessibility which are used in the performance-based allocation process. The region has committed to dedicating 20% of programmed funds to projects that fulfill the regional goals of improving equity and accessibility for 2025 and beyond as a part of the new performance-based capital allocation process

The Service Boards have met and exceeded the 20% goal for the 2025-2028 budget years.

Detailed analysis of the capital evaluation metrics is included in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

Agency Priority Project Mode 2025 Funding 2025-2029 Funding 10 Year Funding Needed 10 Year Unfunded Need
+ CTA Replacement Bus Purchase (4300 series) - Electric Buses Rail $0 $0 $140,000,000 $140,000,000

Ongoing need to replace diesel articulated buses as they age with electric buses.

+ CTA Replacement Buses (4000 Series) - Electric Buses Bus $0 $304,736,456 $351,520,000 $46,783,544

Replace 208 Articulated Buses due replacement in 2023. Ongoing need to replace buses as they age.

Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ Purchase Articulated Electric Buses and Charging Equipment Rolling Stock Bus $0 $304,736,456

Project Details

Description
Funding will provide for a new procurement intended to replace 208 articulated 4000-Series buses with the equivalent number of electric buses
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $221,470,024 $221,470,024
State $0 $0 $62,105,175 $62,105,175
RTA $0 $0 $21,161,257 $21,161,257
Service Board / Local $0 $0 $0 $0
Total $29,336,647 $0 $304,736,456 $334,073,103

Last Updated 12.19.2024

+ RTA RTA Funding Program(s) System $0 $0 $0 $0

Projects and programs undertaken by RTA.

Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ RTA TBD Systemwide System $0 $0

Project Details

Description
Projects TBD
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

Last Updated 12.16.2022

+ Pace Security, Computer, Software, and Office Systems Upgrades Bus $0 $0 $31,936,495 $31,936,495

Upgrade systems to provide enhanced asset protection and business systems.

Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ Computer Systems - Hardware & Software Support Facilities & Equipment Bus $0 $0 ✔︎

Project Details

Description
Computer Systems/Hardware & Software - Projects in 2021 include upgrades, licenses, and training for Hastus route-scheduling software, RideCheck ridership data software, ArcGIS software, and the Pace website. Procurement of digital screens for the interior of buses is also included.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,575,000 $0 $0 $1,575,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,100,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project is underway, and Pace executed a contract for redesigning Pace’s website. Activity continued with bids being evaluated for the procurement of onboard digital screens for the interior of the buses and the contract execution is expected in the next reporting period. Additional tasks will be added throughout the duration of this project.

Last Updated 09.25.2024

+ Mobility as a Service Software Support Facilities & Equipment Bus $0 $0

Project Details

Description
Purchase of Mobility as a Service (MaaS) software
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,398,000 $0 $0 $2,398,000

Last Updated 12.14.2023

+ Onboard Digital Screens Support Facilities & Equipment Bus $0 $0

Project Details

Description
Purchase and install digital screens inside existing buses to display passenger information, such as next-stop announcements, detour notices, and passenger notices.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,477,010 $0 $0 $4,477,010

Last Updated 12.14.2023

+ CTA Signal Replacement (Systemwide) Rail $0 $0 $716,469,000 $716,469,000

Replace Signal System for Ravenswood (Brown), Evanston (Purple), Skokie (Yellow), and Lake (Green) branches.

+ CTA Station Communication Infrastructure Rail $0 $0 $210,200,000 $210,200,000

These are all the life safety mission critical systems which all have to be upgraded at the same time, and are all interrelated. For example the rail station commmunications infrastructure upgrades are needed by PA system, the digital signage system, cameras system, telephone system, radio system etc.

+ Pace Support Equipment/Non-Revenue Vehicles Bus $0 $0 $22,450,000 $22,450,000

Facility and system maintenance equipment and vehicles.

Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ Support Equipment - Non-Revenue Vehicles Support Facilities & Equipment Bus $0 $0

Project Details

Description
Support Equipment/Non-Revenue Vehicles - Projects in 2021 include the purchase of 18 compact SUVs and one minivan with wheelchair ramp.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,400,000 $0 $0 $1,400,000

Last Updated 12.16.2022

+ CTA Systemwide Structural Renewal Rail $0 $46,780,000 $336,200,000 $289,420,000

State of Good Repair projects on CTA 'L' structure.

Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ Embankment and Viaduct Rehabilitation - Systemwide Track & Structure Rail $0 $46,780,000

Project Details

Description
Project funds will be used to rehabilitate embankment and viaduct structures systemwide. These structures aretypically layered earthwork structure with concrete retaining walls that supports tracks, platforms, and/or station houseson a raised area. Spalling can cause the concrete to chip or break off into large pieces, which can create a safety hazard,public injury, and loss of public property (e.g., damage to parked cars along the embankment).
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $22,102,000 $22,102,000
State $0 $0 $24,678,000 $24,678,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $46,780,000 $46,780,000

Last Updated 12.19.2024

+ Harlem Bus Bridge Track & Structure Bus $0 $0 ✔︎

Project Details

Description
This project will replace the Harlem Bus Bridge at our O'Hare Line Harlem Station. The bridge removal and reconstruction limits are from the north end of the bridge expansion joint to the south limits of the bridge expansion joint. The work includes all removal and reconstruction of the existing bridge structure with a new superstructure galvanized steel and bearing assemblies, concrete bridge deck, concrete sidewalks, approach slabs, curb and gutters, drainage, expansion joint assemblies, guard rails, trash enclosures, pedestrian shelters, electrical I LED lighting, signage, pavement stripping, and curb lane painting.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $36,688,972 $0 $0 $36,688,972

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$39,982,424
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The Notice to Proceed for construction has been issued in September 2023. Bridge demolition is still ongoing and I-Beams are being removed with the assistance of a crane. Deck spans continue to be removed. Watermain revisions are under review with OUC for permits.

Last Updated 09.25.2024

+ Infrastructure State of Good Repair Program Track & Structure System $0 $100,000,000

Project Details

Description
Project funds will be targeted to Safety and State of Good Repair projects throughout CTA’s right-of-way infrastructure. All work planned and performed will maintain the asset(s) in proper condition through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset. Funding will provide for the replacement of ties, running rail and third rail on the elevated structure systemwide. Beyond track renewal, work will focus on key deficient structural elements that have been identified through structural inspections.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $90,100,000 $90,100,000
State $0 $0 $9,900,000 $9,900,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $100,000,000 $100,000,000

Last Updated 12.14.2023

+ CTA Systemwide Track Renewal Rail $0 $81,295,000 $395,610,731 $314,315,731

Track improvements to address the most immediate critical track needs throughout the CTA rail system.

Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ Congress Blue Line - P1 Track Track & Structure Rail $0 $0

Project Details

Description
The project includes various priority trackwork on the Blue Line Congress branch.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,500,000 $0 $0 $2,500,000

Last Updated 12.16.2022

+ Congress Line (Fast Tracks) Track & Structure Rail $0 $0

Project Details

Description
This project will replace rails, bars, plates, and address causes of water infiltration in Dearborn Subway between LaSalle and south portal.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,024,058 $0 $0 $7,024,058

Last Updated 12.16.2022

+ DC Breaker Replacement Track & Structure Rail $0 $0

Project Details

Description
The CTA has identified additional traction power needs based on results from the Blue Line Load Flow study. These needs are targeted traction power improvements on the Blue Line such as AC/DC breaker replacement, transformer replacements, upgrading 3rd rail gap cabling, and upgrading getaway cabling and switches. The focus project for this PPS is DC breaker replacement at five existing substations with some associated state of good repair work as funding allows. These five substations and their proposed work are listed below by location: Franklin: 4 DC Feeder breakers, 3 cathode breakers, 2 ELF breakers and 1 Auxiliary Cubicle; Nagle: 4 DC Feeder breakers, 3 cathode breakers, 6 AC breaker replacement Kedvale: 4 DC Feeder breakers, 3 cathode breakers, 1 Emergency Exit Door Edmunds: 4 DC Feeder breakers, 3 cathode breakers, 3 rectifier replacement, 3 bus duct replacement, modify existing Emergency Exit door; Sacramento: 4 DC Feeder breakers, 3 cathode breakers 1. Provide design and engineering services in accordance with the Manual of Procedures for Architectural and Engineering Services and the following design efforts for this project. 2. Remove all existing equipment including, but not limited to, DC switchgear assemblies, AC Breakers (Nagle only), Rectifiers and Duct Banks (Edmunds only), relays, interconnection power and control cables connected between the traction power equipment, and SCADA RTU’s and related appurtenances. 3. Furnish and install new DC switchgear including feeder breakers, cathode breakers, ELF breakers (Franklin only) and AC Breakers (Nagle only), within new cubicles as outlined above for each substation. Provide an auxiliary cubicle. Furnish and install new Rectifiers and Duct Banks at Edmunds only. 4. Provide all required cabling and terminations. 5. Provide all factory testing, startup, and commissioning.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,934,204 $0 $0 $1,934,204

Last Updated 09.25.2024

+ DC Breakers (Fast Tracks) Track & Structure Rail $0 $0

Project Details

Description
This project will replace DC breakers in Sacramento, Franklin, and Nagle Substations. This DC breaker replacement may require some changes to the organization of other equipment inside the substation.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $6,571,295 $0 $0 $6,571,295

Last Updated 12.16.2022

+ Green & Pink Line West - Track Improvements Track & Structure Rail $0 $0

Project Details

Description
Green & Pink Line West - Track Improvements (GTT) Tower 18 to the Paulina Connector- Preserve the integrity of Lake St Elevated tracks through replacement of ties, fasteners, footwalks, improved curve geometry, and rail grinding as well as replacing the top flange as necessary.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,308,465 $0 $0 $1,308,465

Last Updated 12.16.2022

+ Nagle Curve Improvements Track & Structure Rail $0 $0

Project Details

Description
This project includes removing and replacing existing rail in the Nagle Curve area on the O’Hare Branch of the Blue Line. Project replaces the existing rail with new continuous welded rail at Nagle Curve. The new rail will be set into the existing plates with 100% replacement of double studded pads, heavy duty insulators, and pandrol e-clips. Work also includes a track survey to record the track geometry (profile, alignment, cross level and gauge), clearances, and the location of the track.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $75,004 $0 $0 $75,004

Last Updated 12.16.2022

+ North Mainline - Special Track and Geometry Improvements Track & Structure Rail $0 $49,365,000

Project Details

Description
Project funds will provide for replaces the ties, track planking, turnout plates, diamond plates, fasteners, and contact rail chairs in the special trackwork at Belden, Altgeld, Oakdale, and Barry interlockings. The curves that are being proposed to be modified are north and south of Fullerton Station, north of the Diversey Station, guarded curves over George Street, and curves south of the Belmont Station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $39,143,000 $39,143,000
State $0 $0 $10,222,000 $10,222,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $49,365,000 $49,365,000

Last Updated 12.19.2024

+ North Mainline – Armitage Interlocking Special Track Improvements Track & Structure Rail $0 $31,930,000

Project Details

Description
Project funds will provide for replacement of the ties, track planking, turnout plates, diamond plates, fasteners, and contact rail chairs in the special trackwork at Belden, Altgeld, Oakdale, and Barry interlockings. The curves that are being proposed to be modified are north and south of Fullerton Station, north of the Diversey Station, guarded curves over George Street, and curves south of the Belmont Station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $31,930,000 $31,930,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $31,930,000 $31,930,000

Last Updated 12.19.2024

+ Red & Blue Line Subway - Track Improvements Track & Structure Rail $0 $0

Project Details

Description
Red & Blue Line Subway - Track Improvements (GTT) - Dearborn Subway Water Management and Track Improvements - This is a targeted project to replace assets that have been deteriorated by water infiltration. Work includes replace select rail, rail fasteners and direct fixation concrete ties, grind 100% of the running rail, and select drainage improvements
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $5,639,070 $0 $0 $5,639,070

Last Updated 12.16.2022

+ Rehabilitate Blue Line - Kimball Subway Waterproofing Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Subway Waterproofing & Track - Funding will provide for critical waterproofing patchwork needed to continue rail service through the Blue Line O'Hare branch.. Due to funding restrictions CTA cannot move forward with original scope of work to mitigate water infiltration in the Dearborn subway.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,120,513 $0 $0 $4,120,513

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$7,785,710
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Work activities under this project are ongoing. The waterproofing and grout injection work is performed by CTA forces whenever single-track access is available.

Last Updated 06.10.2024

+ Roosevelt Station - Elevated Track Rehabilitation Track & Structure Rail $0 $0

Project Details

Description
This job is a 100% replacement of cross ties, plates and fasteners throughout the length of Roosevelt elevated station on the Northbound track. The railroad track in the platform area has several wide gage defects which require a slow zone. The wide gage is due to failing ties and failing plates. Footwalk ties in the area are also in bad condition, so new footwalk will be added after the track rehabilitation.Track geometry will be fixed with this project, removing wide gage defects and the slow zones associated with the defects. Poor footwalk conditions will also be removed from the track as the carpenters install 100% new footwalk material.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,000,904 $0 $0 $1,000,904

Last Updated 09.25.2024

+ Third Rail Isolation Demonstration Project Track & Structure Rail $0 $0

Project Details

Description
CTA utilizes an exposed third rail system to provide power to trains on all revenue and non-revenue tracks. The third rail is typically installed on insulator chairs spaced eight feet apart just outside one of the running rails. CTA's rail cars utilize a “gravity shoe” to collect 600 Volts DC from the top surface of the third rail. In station areas, the third rail is typically located on the opposite side of the track from the station platform – this provides some level of protection from a person falling off the platform and coming in contact with the electrified third rail. Unfortunately, there are incidences when a passenger falls off the platform with sufficient momentum to reach the far side of the track and make contact with the third rail. This proposed project will add additional safety features on the third rail in the vicinity of station platforms.Funding will provide for two technologies: the Third Rail Isolation System and the Third Rail Side Guards (sideboards).The first feature is a safety feature proposed to include the isolation of the third rail through the stations such that when no train is approaching or present at the station, the third rail would be de-energized. This additional feature would include a control device to energize the third rail in the station, and by-pass cables to carry current around the station to feed the third rail outside the station.The second feature would include non-conductive side boards on both sides of the third rail which would reduce the likelihood of a person making contact with the rail. The sideboards would also provide an opportunity to apply warning labels directly on the third rail so as to better direct passengers to the hazard posed by this element. The sideboards would also provide a layer of protection for CTA employees that are required to walk alongside the third rail during maintenance activities.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,478,864 $0 $0 $1,478,864

Last Updated 12.16.2022

+ CTA Tactical Signal Improvements Rail $0 $0 $21,630,000 $21,630,000

State of Good Repair projects and replacing obsolete equipment on CTA rail signal system.

Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ Tactical Traction Power (Equipment/Cable/Enclosures) Track & Structure Rail $0 $0 ✔︎

Project Details

Description
State of Good Repair projects and replacing obsolete equipment on CTA rail signal system
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $18,586,628 $0 $0 $18,586,628

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$10,293,685
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Permits for the project were received in the last reporting period. Currently, the General Contractor is submitting process plans for start of construction and mobilization on site. Delivery of onsite storage containers is ongoing. CTA is working with the contractor to start the first phase of the project, which is the electrical shop equipment relocation.

Last Updated 12.14.2023