Planning Programs and Projects
This page allows users to search for projects from the RTA’s Planning Programs. Users can search for projects by name or keyword from the Search bar or the Filter pulldown menus.
Table results display summary information about each project. To view more details for a project, select the + icon to expand the view for additional information.
Year | Project Title | Program | Project Type | Project Partner | Budget | Funding Source(s) | Status | |||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
+ | Ride Lake County West '11 | Section 5310 / JARC / NF | Operating | Lake County | $1,000,000 |
|
Completed | |||||||
Project DetailsRelated Reports
Not Available Description
This dial-a-ride service will operate weekdays in Antioch, Avon, Grant, and Lake Villa townships. A portion of the service will be a flexible route connecting three Metra stations on the NCS Line and Milwaukee District - North Line with residential areas to offer greater access to employment opportunities primarily for individuals with limited mobility and other transit dependent populations. The service expanded its boundaries in December 2012 to include Waconda and Fremont Townships. Lake County implemented the service January 11, 2010.
Current Activities
The service provided 447 trips in June 2018.
This project is complete.
Funding Amounts by Source
Last Updated 06.13.2019 |
||||||||||||||
+ | Rolling Meadows Golf Road Transit and Pedestrian Mobility Study | Community Planning | Transit Improvement Plan | Rolling Meadows | $88,760 |
|
Completed | |||||||
Project DetailsRelated Reports
Description
This project provided recommendations aimed at improving pedestrian access, circulation and safety along Golf Road (IL Route 58) from Interstate 290 (IL Route 53) to Algonquin Road (IL Route 62), a 2 mile corridor that is home to several thousand professional jobs. The study focused on ways to make the area transit and pedestrian friendly, and examined the possibility of increased local transit service.
Current Activities
The final plan was presented to and approved by the City Council on March 19, 2013. An Implementation Task Force has been formed and continues to pursue funding options for plan recommendations, particularly pedestrian improvements and additional shuttle service.
The City received Congestion Mitigation and Air Quality (CMAQ) funding, via the RTA's Access to Transit Improvement Program, to install two pedestrian signal heads, two miles of sidewalks, and five crosswalks in the study area. Installation of these improvements was completed in late 2016. Pace initiated Call-n-Ride service for the corridor in October 2012. Additionally, the Implementation Task Force is working with the TMA of Lake Cook to investigate possible Shuttle Bug service. Funding Amounts by Source
Last Updated 05.31.2017 |
||||||||||||||
+ | Romeoville East Side Plan | Community Planning | Transit-Oriented Development Plan | Romeoville | $99,950 |
|
Completed | |||||||
Project DetailsRelated Reports
Description
This project created a station area plan for the new Romeoville Metra station, a planned intermediate stop on Metra's Heritage Corridor Line. The plan includes land use, circulation and connectivity plans that complement the new station and recommends transit options to connect the new station area to rest of the community. Current Activities
The Village Board unanimously adopted the Romeoville East Side Plan on April 18, 2012 as an amendment to the Village's Comprehensive plan. In 2013 Metra included this new station/stop as part of the 2013-2017 Capital Projects Program and is currently exploring ways to obtain the necessary funding to move forward. Funding Amounts by Source
Last Updated 07.28.2021 |
||||||||||||||
+ | Volunteer Express '11 | Section 5310 / JARC / NF | Operating | Hanover Township | $15,454 |
|
Completed | |||||||
Project DetailsRelated Reports
Not Available Description
Funding for this project will support a volunteer driver program supplementing the services offered by Hanover Township's Dial-A-Bus program. Volunteer drivers utilizing their own vehicles will provide the door-to-door service. Local share will be provided with transportation development credits, formerly known as toll credits.
Current Activities
The service provided 24 trips in November 2014. This project is complete.
Funding Amounts by Source
Last Updated 08.28.2018 |
||||||||||||||
+ | Will County Mobility Management Program '11 | Section 5310 / JARC / NF | Capital - Operating - Mobility Management | Will County | $892,000 |
|
Completed | |||||||
Project DetailsRelated Reports
Not Available Description
This program provides transportation and mobility management services for persons with disabilities, the elderly and low-income individuals residing in eastern Will County townships. The program is an outgrowth of the county's coordinated paratransit plan funded through the RTA's Subregional Planning program. The RTA Board approved the 2011 Program of Projects at its November 16, 2011 meeting. Grant agreements have been executed. By agreement with Washington Township this project has taken on the management responsibilities for grants initially awarded to Washington Township. As a result of this agreement an additional $32,970 in federal funding has been added to this project. Will County formed the Paratransit Council that will help to set policy for the project. This program provides transportation and mobility services seniors and individuals with disabilities residing in eastern Will County townships. Current Activities
The JARC service provided 228 trips in August 2018. This project is complete. Funding Amounts by Source
Last Updated 11.08.2021 |
||||||||||||||
+ | Chicago South Lakefront Corridor Transit Study | Community Planning | Transit Improvement Plan | Chicago | $449,945 |
|
Completed | |||||||
Project DetailsDescription
The purpose of this study was to identify public transportation improvements that will enhance mobility for residents of the study area communities and increase access to jobs located throughout the city and surrounding areas. The South Lakefront study area borders are the lakefront on the east; the Stevenson Expressway on the north; the Dan Ryan Expressway, Norfolk Southern rail yard and Cottage Grove Avenue on the west; and 95th Street on the south.
Over the last 20 years, the city, businesses, and the civic community have demonstrated strong leadership and commitment in working to address many of the economic and social challenges in the study area. This study further supports this ongoing commitment by encouraging dialogue among area residents, community leaders, institutions, developers, and city and regional transit and transportation officials.
The study developed consensus on the main transit-related issues and problems in the study area and on the most important transit system investments and related community development projects so that they can be advanced to more detailed study.
Current Activities
CDOT allocated $260,000 in CMAQ funding to construct pedestrian access improvements at the 35th / IIT Green Line Station. Improvements included a pedestrian plaza, pedestrian countdown signals, crosswalks, curb bump-outs and signal timing improvements on 35th Street to improve traffic flow. To further enhance the connectivity to this station the CTA extended service on the #35 31st / 35th bus route west to Cicero Avenue. Tribune article: http://www.chicagotribune.com/news/local/ct-met-cta-35-bus-1010-20131010,0,5789910.story
In 2015 the CTA was awarded funds from the RTA's Community Planning program to study the slow bus service along the 79th street corridor and to identify ways to improve the slow zones, thus restoring the reliability of this important and busy bus route. This study was completed in 2018 and can be found on RTAMS. Funding Amounts by Source
Last Updated 10.30.2018 |
||||||||||||||
+ | Chicago Washington Park 63rd Street Corridor TOD Study | Community Planning | Transit-Oriented Development Plan | Chicago | $149,979 |
|
Completed | |||||||
Project DetailsRelated Reports
Description
This project created a transit access improvement and transit-oriented development (TOD) plan for the 63rd Street Corridor in Chicago's Washington Park Neighborhood between the Cottage Grove Green Line station on the east and the King Drive Green Line station on the west. The plan outlines land use development concepts, design guidelines, and implementation strategies for access improvements and TOD along the corridor that will help maximize the existing transit investments within the neighborhood, including CTA bus routes (Route 63, which ranks ninth in overall bus ridership for the CTA) and rail services. The plan serves as a guide to enhance development, increase transit ridership and expand housing and economic development opportunities in the neighborhood. Current Activities
This study is being used by City staff and elected officials to guide transit access improvements and land use development along the corridor. A significant amount of development has been occurring near the station. Visit our Story Map for details Funding Amounts by Source
Last Updated 07.28.2021 |
||||||||||||||
+ | Clarendon Hills Train Station Redevelopment Phase I Implementation | Community Planning | Transit-Oriented Development Plan | Clarendon Hills | $99,980 |
|
Completed | |||||||
Project DetailsDescription
This project resulted in a phased implementation plan for advancing the redevelopment of the Clarendon Hills Metra Station area. The Village completed a transit-oriented development study for their Metra Station area in 2006; this project further refined the recommendations from that study, focusing specifically on the train station and commuter lot redevelopment. The implementation plan recommended two redevelopment alternatives. The near-term plan recommended access improvements, including a pedestrian underpass under the tracks, and revitalization of the existing station house. The long-term plan builds on the near-term plans and recommends a full redevelopment of the current commuter lot into a parking deck, commercial space and a new station house. The final report was adopted by the Village Board in March 2012. Current Activities
Within the development area identified in the Clarendon Hills TOD plan, In 2018 two mixed-use developments were constructed within the development area identified in the Clarendon Hills TOD plan, a four-story development with 42 apartment units with 900 square feet of street level commercial at the corner of Park and Walker Avenue, and at the corner of Park and Prospect Avenues, 88 Park Avenue was completed as a three story 8-unit apartment building. Both of these projects are within a two to three block walk of the Metra station and the adjoining Pace Bus stop in downtown Clarendon Hills. In May of 2018 Clarendon Hills received an Illinois Transportation Enhancement Program (ITEP) grant for new railroad crossings gates at Prospect Avenue; improved pedestrian crossings and corner bump out enhancements at Prospect Avenue, Burlington Avenue, and Eastern Avenue/Anne Streets; installation/enhancement of bicycle lockup areas and shelters north and south of BNSF; development of a defined kiss-and-ride north of BNSF; and other streetscape improvements including plaza development, benches and street landscaping. Reconstruction of the Clarendon Hills commuter station was completed in 2022. In addition to station improvements, the Village incorportated streetscape improvements that created a shared vehicle/bike lane, and reduced the distance pedestrians must walk to cross the street. Funding Amounts by Source
Last Updated 10.24.2022 |
||||||||||||||
+ | Concrete Waiting Areas at Bus Stops | Section 5310 / JARC / NF | Capital | Pace Suburban Bus | $600,000 |
|
Completed | |||||||
Project DetailsRelated Reports
Not Available Description
Pace will construct up to 150 concrete pads and ancillary connections to accessible paths at Pace bus stops throughout their service area. The pads would be located against a raised curb to facilitate "level boarding" from the pad to the buses bottom stop or provide a landing area for a wheelchair lift. This project is matched with Transportation Development Credits.
Current Activities
Pace, from an initial list of 191 candidate stops, has completed improvements at 65 locations. At the end of March 2013, the last series of improvements were made at:
162nd/Woodlawn, SW, South Holland;
Cermak at Boeger, NE, Westchester;
Cermak at Boeger, SW, Westchester;
Randall Rd at Wilson St, SB, Batavia (shelter installation);
Halsted St at 171st St, South Holland (shelter installation); and
159th at Pulaski, NW, Markham.
The project is complete.
Funding Amounts by Source
Last Updated 09.17.2014 |
||||||||||||||
+ | Geneva Downtown / Station Area Master Plan | Community Planning | Transit-Oriented Development Plan | Geneva | $124,081 |
|
Completed | |||||||
Project DetailsRelated Reports
Description
This project created a transit-oriented development plan for an approximate ½ mile radius of the Geneva Metra Station. The plan recommendations focused on the expansion of retail development, increasing housing diversity, mixed-use development, parking expansion and improving access to and around the station. The final report consists of an existing conditions report, market analysis, concept plan, parking and circulation plan, design guidelines and implementation recommendations.
Current Activities
The plan was formally approved as an amendment to the Geneva Comprehensive Plan in November 2012. In May 2015, the City completed construction of a third tier on the Third Street parking deck, adding an additional 180 spaces.
Geneva continues to build transit supportive infill residential development per the plan recommendations. Two recent developments are noteworthy Campbell Row and Park Place, both completed in 2017. Campbell Row is a 5-unit townhome development at the corner of Campbell and Fourth Streets, 1/3 of a mile from the Geneva Metra station and within two blocks of Pace routes 801 and 802. Park Place is a 30-unit row house development at the corner of First and Stevens within 3/4 mile of the Metra station and Pace bus routes. In addition, in August 2019, approval took place for Phase I of Hamilton Place, which includes the construction of 16 single-family homes at the Northeast corner of Richards & State street. Funding Amounts by Source
Last Updated 09.16.2019 |