Project Management Oversight (PMO) Capital Projects
The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently. The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.
Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.
PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site. The latest report is the June 2023 Project Management Oversight report.
Agency | Project Title | Asset Category | Mode | 2025 Funding | 2025-2029 Funding | Status | |||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
+ | Metra | CREATE - 75th CIP Rock Island District Connection | Track & Structure | Rail | $0 | $0 | Behind Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project will provide engineering for the 75th Street Corridor Improvement Project (CIP) that will relieve rail congestion by separating freight and passenger rail lines in the City of Chicago. The eventual construction phases will construct a flyover to connect Metra Southwest Service (SWS) to the Rock Island (RID) Line at 73rd Street. Constructing the project will eliminate a major conflict point between Metra and freight trains, and train idling will be reduced. This funding represents Metra’s contribution to the project, other project partners within CREATE will contribute additional funding.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The design development is advancing to 90%. Coordination with a Norfolk Southern project is ongoing. Work is progressing on Right-of-Way assessment and property acquisition assessment. There was also an executed change order to add a pedestrian tunnel for the project. Finally, the Forest Hill Flyover construction work continued during this reporting period.
Last Updated 09.25.2024 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Crew Facilities | Support Facilities & Equipment | Rail | $0 | $0 | Behind Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project includes, but is not limited to, renovation of existing crew facilities or construction of new crew facilities at existing yard locations across the Metra system. Work may include design of and renovations to interior spaces such as office spaces, locker rooms, and training facilities.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Metra is working on projects at four facilities. Metra will build a new crew facility at Fox Lake Station on the Milwaukee North District Line. The Notice to Proceed for construction has been issued. The contractor is currently working on submittals and permitting. The procurement activities for the Western Ave facility design are ongoing. The National Environmental Policy Act (NEPA) activities for the University Park and Elgin design are in progress.
Last Updated 06.10.2024 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | CTA | CTA Open Fare Payment System - Equipment (Lease) - VENTRA | Support Facilities & Equipment | System | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
CTA Open Fare Payment System - Equipment (Lease) - VENTRA: funds will provide in part for the principal and interest of the agreement need for the Open Fare Standard equipment, hardware, and software costs.The contractor (Cubic) costs including, but are not limited to, expenses incurred to design, build, finance, operate, maintain, repair and replace the equipment, the software and the Open Standards Fare System, and provide the Services, in accordance with the specifications and performance at the service levels and perform any other obligations pursuant to this Agreement.The capital share of the annual Base component cost is $15 million which provides for necessary design, testing, purchase and installation of assets such as the following: Ventra Vending Machines, Mobile Data Validators (readers), Driver Terminal Displays, retail terminals, and B26all software applications, and back-end hardware.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
This project is for the 2020, 2021, 2022, and 2023 annual equipment lease. The annual 2023 payments for the equipment lease were completed for this open fare equipment. This will be the final update on this project.
Last Updated 06.10.2024 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Elevator Replacement | Stations & Passenger Facilities | Rail | $0 | $8,986,515 | Behind Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project will renovate, replace, or upgrade elevators at various locations throughout the entire Metra system. New elevators will be built to the industry best practice specifications set by the American Public Transportation Association (APTA) to ensure the new elevators are reliable and resilient as well as ADA-compliant. This project is part of Metra’s ongoing commitment to achieving full accessibility across the system.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The elevator modernization for Millennium Station and Grand & Cicero are in the design development phase with 60% design under review and incorporating comments. Metra is also working on task order amendments. A systemwide elevator inspection and assessment is in progress as well as having proposals being evaluated.
Last Updated 12.19.2024 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Elmhurst Station | Stations & Passenger Facilities | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project will fund Metra’s portion of a larger station renovation/expansion in Elmhurst. It will leverage CMAQ funds obtained by the Village of Elmhurst to construct a larger station to accommodate the growing ridership.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Preliminary engineering and NEPA process were completed. The Village of Elmhurst is leading the design with their consultant. The designer reached 90% design and is under Metra review. The development to 100% design has been initiated.
Last Updated 09.25.2024 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Evanston Bridge Repainting | Track & Structure | Rail | $0 | $0 | Behind Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project involves the sanding, abatement and repainting of the Dempster Street and Davis Streetbridges in Evanston on the Union Pacific North Line.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The contractor finished painting and applying the protective coating on the bridge in December. Final invoices remain and this will be the final update on this project.
Last Updated 06.22.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | CTA | Facilities Critical Needs - Forest Glen Building Demolition | Support Facilities & Equipment | Bus | $0 | $0 | Behind Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
The purpose of this project is to eliminate building maintenance costs and security liabilities to CTA associated with the vacant buildings at the Forest Glen Bus Garage (located at 5353 W. Armstrong Avenue and 5601 N. Elston Avenue), as well as to provide additional capacity for bus parking at the Forest Glen Bus Garage. The project scope includes demolition of the buildings at 5353 W. Armstrong Avenue, 5601 N. Elston Avenue, and the existing salt shed (all currently owned by the CTA).
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Both of the vacant buildings have been demolished and the debris has been removed from the site. Fencing has been installed around the vacant lot. This project was significantly delayed due to the extensive environmental abatement process that was not initially anticipated. Final invoicing related to this process is outstanding. This is the final report on this project.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | CTA | Facilities Critical Needs - Kedzie Bus Garage Façade | Support Facilities & Equipment | Bus | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
The project will retain a DoR firm to complete a comprehensive assessment of the structure’s exterior envelope to develop remediation and/or replacement plans for concerns regarding the exterior brick veneer delaminating from the backing block. The work will include detailing for caulking, flashing, or other treatments to prevent future similar issues from occurring due to water infiltration. Construction will repair portions of the brick that have fallen from the structure and other repairs to prevent recurrence of the failure.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The project was on a brief hold in the winter due to weather conditions. The contractor has re-mobilized and work on concrete repairs, expansion joints, joint sealers and thermal insulation is ongoing. The tuckpointing and roofing work is also in progress.
Last Updated 06.10.2024 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | CTA | Facilities Critical Needs- Substation Roof Repairs - Phase II | Support Facilities & Equipment | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Program would address the most immediate critical needs at CTA facilities systemwide to enable their safe and reliable operation. The goal would be to have an annual appropriation in the CIP that would be solely dedicated toward addressing this Program. Transit service safety and reliability is affected by out-of-date rail, bus, and maintenance facilities.The project will complete roof replacements at five CTA substations: Calvary, Lotus, Des Plaines, Ashland, and O’Hare. The project will also complete exterior façade repair at the O’Hare Substation, including wall panel and louver replacement, masonry wall and expansion joint repairs, painting, doors, and new surface mounted exterior light fixtures. Design will be completed in-house by CTA engineering staff.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Construction has been completed. The roof replacements at seven substations have been completed as well as repairs to the building envelope at O’Hare substation. This project is currently in the close out phase. This is the last report on this project.
Last Updated 06.10.2024 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Pace | Farebox System Replacement | Support Facilities & Equipment | Bus | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Farebox System Replacement - Over 700 fareboxes on Pace fixed route buses will be replaced, with prior PAYGO funding of $7.5M from 2020 included.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
All of the fareboxes were installed on the garages and the project is considered substantially complete. Final invoices remain. This will be the final update on this project.
Last Updated 04.01.2024 |