Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the June 2023 Project Management Oversight report

i

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Project Title Asset Category Mode 2025 Funding 2025-2029 Funding Status
+ Pace Purchase 30' Diesel Buses Rolling Stock Bus $0 $0 On Schedule

Project Details

Description
This project is a new contract awarded in September 2019 for a new five?yearindefinite delivery/indefinite quantity contract for 30’ low floor diesel buses. Theminimum quantity to be purchased under this contract is 67 buses and the totalnumber of buses procured will not exceed the maximum amount of 164.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,500,000 $0 $0 $4,500,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$80,261,908
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
A total of 67 buses have been ordered to date. The first order consisted of 23 buses, all of which are in service. These were delayed due to the COVID-19 crisis. The second order consisted of 44 buses. All of the buses under the second order were received, with the final bus delivered in February 2023. The buses service the areas currently serviced by Fox Valley and Batavia. Pace will not pursue purchasing anymore buses under this contract. This will be the final update on this project.

Last Updated 04.01.2024

+ Pace Purchase 40' Diesel Buses Rolling Stock Bus $0 $0 On Schedule

Project Details

Description
Replacement diesel buses (40') - Pace plans to replace 78 diesel buses including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections).
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$41,786,531
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Pace placed an order for the delivery of a total of 85 buses. To date, all 85 buses have been received and are in service. The buses are expected to service the routes currently serviced by West Division. This will be the final update on this project.

Last Updated 12.14.2023

+ Pace Purchase 40' Low-Floor CNG Buses Rolling Stock Bus $0 $0 On Schedule

Project Details

Description
Pace will purchase 40FT CNG Buses.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$75,896,625
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Pace awarded a new contract for the purchase of additional vehicles in March 2022. The first order was a quantity of 47 CNG buses. The production of these vehicles has been put on hold during this reporting period. A portion of these vehicles will be utilized at the Northwest Wheeling Garage, which is an ongoing project. As Pace establishes a construction schedule for the Wheeling Garage, a production scheduled will be developed for the order of 47 buses. Pace may reevaluate purchasing CNG buses vs electric buses as well.

Last Updated 06.10.2024

+ CTA Purchase Rail Cars - 7000 Series (Base Order 400) Rolling Stock Rail $0 $30,334,196 On Schedule

Project Details

Description
Purchase Rail Cars - 7000' Series (Base Order 400) - Program funds will provide for the continued cash needs and obligation provisions as identified in the contract documents for the 7000' series rail car Base contract order of 400 cars.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $15,334,196 $15,334,196
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
$15,000,000 $15,000,000
Total $230,871,720 $0 $30,334,196 $261,205,916

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$713,703,634
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Status conferences continued with CRRC to address/track various items. Production deliveries continued during this reporting period. CTA inspection personnel continue working in China and continue to conduct welded subassembly checks and production car body shell inspections for production cars. There are approximately 90 car body shells in various states of assembly or being delivered to Chicago. Final assembly continues on 36 cars in the US and final inspections on 12 cars were underway at the Skokie Shops. CTA has accepted 88 of the cars thus far for revenue service.

Last Updated 12.19.2024

+ CTA Purchase up to 70 Electric Buses and up to 9 Charging Stations Rolling Stock Bus $0 $0 On Schedule

Project Details

Description
Purchase up to 70 Electric Buses and up to nine Chargers - Bus funding provides for a future order of up to 70 40-foot battery-powered, zero-emission, all-electric, fully accessible, public transit buses with en-route charging capabilities. CTA will retire up to 70 1000-Series New Flyer buses that are over 14 years old. Turnkey project to procure Electric buses and associated charging infrastructure.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $23,541,688 $0 $0 $23,541,688

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$71,991,905
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The charging stations were received and installed and reached substantial completion in January 2021. In Q4-2021, seventeen (17) production buses were completed and delivered to CTA. The installation of revenue fare collection systems, communication equipment, network systems were completed in Q2-2022. A total of twenty-three (23) buses were delivered. Nineteen (19) are in service and four are being used at the 74th Garage for operator training. CTA previously exercised an option for an additional twenty-two (22) buses. CTA’s Infrastructure department continued working with Bus Engineering to finalize the budget breakdown and scope for the 103rd Garage. Pre-production activities continued where production is expected to start in June 2025 and delivery of the first vehicle is expected by the end of 2025.

Last Updated 06.10.2024

+ CTA Rail Car Overhaul - 2600-Series Rolling Stock Rail $0 $0 On Schedule

Project Details

Description
This project consists of three phases. Phase A is for rail car motor replacement and was completed in October 2019. Phase B is for procurement and installation ofthe propulsion kits with the parts contract was executed, and kits were received. Work for this phase began in November 2019 and all 90 cars were completed inAugust 2020. Phase C is for the procurement of material contracts and installation. The contract was approved at the October 2020. The first delivery ofmaterial is expected to arrive in May 2021 and the overhaul is expected to take place in the first half of 2022.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$25,314,552
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project consists of three phases. Phase A is for rail car motor replacement and was completed in October 2019. Phase B is for procurement and installation of the propulsion kits with the parts contract was executed, and kits were received. Work for this phase began in November 2019 and all 90 cars were completed in August 2020. Phase C is for the procurement of material contracts and installation. The contract was approved at the October 2020. All cars have completed the overhaul as of March 2022 and this project is considered complete. This will be the final update on this project.

Last Updated 12.14.2023

+ CTA Rail Facilities - Des Plaines Yard Support Facilities & Equipment Rail $0 $0 On Schedule

Project Details

Description
The Rail Facilities State of Good Repair Program focuses on critical improvements at CTA rail yards, which include improvements to the yard infrastructure itself (ties, rail, fasteners, ballast, contact rail etc.) as well as the yard fire suppression systems and lighting. The Des Plaines Yard project will include the reconstruction and reconfiguration of the inner and outer lead tracks, including associated special trackwork. Replacement and reconfiguration of the special trackwork in the east yard storage, including the road crossings to the yard shops will also be completed.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $8,860,092 $0 $0 $8,860,092

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$22,858,137
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The Notice to Proceed for construction services has been issued in January 2024. The contractor has been working on submittals and permitting. Coordination with Nicor Gas for the new gas line is ongoing. Advanced purchased material is being delivered. CTA and the contractor are preparing for a 16-day yard shutdown to perform some of the critical work.

Last Updated 09.25.2024

+ CTA Red/Purple Modernization - Phase 1 Modernization Rail $0 $0 On Schedule

Project Details

Description
North Main Line - RPM The purpose of the Red and Purple Modernization (RPM) Program is to expand capacity to meet growing ridership demand; reduce travel times; improve access to job markets and destinations; better utilize existing transit infrastructure; bring the existing infrastructure to a state of good repair; and improve access to the system for patrons with disabilities. FY2021-2025 funds will continue RPM Phase One funding stream.Red Purple Modernization phase one project consists the following interrelated and concurrent projects, as defined in the environmental documents to be developed by the CTA:RED-PURPLE BYPASS PROJECT. This element would construct a fifth track bypass flyover immediately north of the CTA Belmont Station to separate northbound Brown Line trains that currently conflict with southbound Purple Line trains and both northbound and southbound Red Line trains. This project includes construction of a new fifth track bypass flyover and replacement or renovation of approximately 0.3 mile of associated mainline track.LAWRENCE TO BRYN MAWR MODERNIZATION PROJECT. This modernization project would replace 1.3 miles of the existing rail line from Leland Avenue on the south to approximately Ardmore Avenue on the north. This section of track includes four stations - Lawrence, Argyle, Berwyn, and Bryn Mawr. The project would expand and modernize these four stations. The project would also provide ADA access to transit customers with disabilities in a two-mile stretch of the north Red Line that currently does not have accessible stations.CORRIDOR SIGNAL IMPROVEMENTS. This project would improve the signal system and special trackwork generally between Belmont and Loyola stations. Improvements would occur within CTA's existing right-of-way. The scope of work includes planning, design, procurement, and installation of wayside equipment and special trackwork that are significantly past their useful lives. This project also includes improvements to existing special trackwork.CONTINUED INTERIM CAPITAL IMPROVEMENTS. This project would improve track infrastructure conditions between Belmont Station and Linden Station in order to maintain service along existing rail lines. This work would take place within the CTA's existing right-of-way.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $777,725,323 $0 $0 $777,725,323

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$2,203,408,226
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The Corridor Signal Improvements (CSI) project monitored the track circuit in the LBMM Stage B area and resumed installing brackets and messenger cables along embankment walls north of Thorndale. Additionally, innerduct installation for the communications network backbone continued. The Red Purple Modernization (RPM) project removed the old Clark Relay House, addressed signal testing discrepancies, and prepared for factory tests of new signal equipment. The Jarvis Relay Room began mechanical, electrical, and fire suppression improvements. The Lawrence to Bryn Mawr Modernization (LBMM) completed significant structural work, including embankment excavation, retaining wall removal, and concrete deck pours for the Ardmore transition bridge. Drilling caissons and constructing concrete piers for the elevated structure progressed, and foundational work for the Bryn Mawr station began, alongside steel erection for the platform and escalator/elevator trusses. The

Last Updated 06.10.2024

+ CTA Rehabilitate Blue Line - Kimball Subway Waterproofing Track & Structure Rail $0 $0 On Schedule

Project Details

Description
Subway Waterproofing & Track - Funding will provide for critical waterproofing patchwork needed to continue rail service through the Blue Line O'Hare branch.. Due to funding restrictions CTA cannot move forward with original scope of work to mitigate water infiltration in the Dearborn subway.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,120,513 $0 $0 $4,120,513

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$7,785,710
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Work activities under this project are ongoing. The waterproofing and grout injection work is performed by CTA forces whenever single-track access is available.

Last Updated 06.10.2024

+ Metra Remanufactured Locomotive Purchase Rolling Stock Rail $0 $0 On Schedule

Project Details

Description
This project involves the purchase of up to forty-two (42) remanufactured diesel locomotives. The contract has a base order of fifteen (15) locomotives with three (3) Options to order nine (9) additional locomotives each. Metra ancipicates these locomotives to have increased horsepower, lower emissions, and greater fuel efficiency than the current fleet average.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $215,221,919 $0 $0 $215,221,919

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$195,039,926
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
All 15 locomotives from the base order have been delivered to Metra. Blower fans on all the completed locomotives are in process of being replaced under warranty. Metra also exercised Option 1 under the contract for an additional nine locomotives. Work on Option 1 locomotives is in progress.

Last Updated 12.19.2024