Project Management Oversight (PMO) Capital Projects
The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently. The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.
Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.
PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site. The latest report is the December 2024 Project Management Oversight report.
Toggle | Agency | Project Title | Asset Category | Mode | 2025 Funding | 2025-2029 Funding | Status | ||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
+ | Metra | Rock Island Connection and 3rd track | Track & Structure | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Establish a new 3rd main on the Rock Island Line. The project study limits shall be from MP 0.0 (LaSalle Station) to MP 10.5 (Gresham Jct.). The new 3rd main is anticipated to extend from the new 16th Interlocking at MP 1.0 presently in design to the new CREATE P2 Interlocking at CP 74th. It is also anticpated that a new crossover will be required at Gresham to faciliate train movement into and out of the new 3rd main.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The preliminary engineering for this project has started. The NEPA Scopeof- Work (SOW) was advertised in October 2022. Survey work started in the first week of October 2022 and NEPA activities continue progressing.
Last Updated 06.10.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Seeger Interlocking | Electrical, Signal & Communications | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project will provide funds for the replacement of the Seeger Interlocking on Metra’s Union PacificNorthwest line (MP 18.5). The layout of the control point only allows 30 mph crossover speeds forcommuter trains. The goal of this upgrade, in addition to updating the equipment, would be to increasethe train speeds to 40 mph, and upgrade the switch layouts to meet current railroad designspecification.The existing signal system is approximately 50 years old and requires replacement due to age andcondition. The signal system has had malfunction issues that have caused delays. The replacementequipment will include a modern, solid state control point and an upgraded switch machine.By renewing the signal infrastructure with the latest technologies, Metra can increase operationalefficiency, enhance safety, reduce delays, and have a life expectancy of additional twenty plus years.FY2020 PAYGO funds will be used to implement this project.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The status for this project is completed and final bills remain. This will be the final update on this project.
Last Updated 03.27.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Pace | South Campus Project - Markham | Support Facilities & Equipment | Bus | $0 | $0 | Behind Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project will provide for construction, project management oversight, project administration, and any associated equipment and services for the Pace South Campus project. New facilities will be built on a 22-acre site that is situated next door to Pace’s South Division (2107 W. 163rd Place) Garage in Markham, Illinois, which is already owned by Pace. The purpose of this project is to consolidate certain operational functions currently operating at each garage into one location.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The office building has been completed and Pace held an opening ceremony in July 2024. The installation of the fire suppression system at the Acceptance Facility has been finalized and the project has reached substantial completion. Project close out activities are in progress. This is the last report on this project.
Last Updated 06.10.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Station Displays (TROI Net) | Stations & Passenger Facilities | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
The TROI-Net Station Displays Project is the design and rollout of the next generation of Metra's VIS Signs as they reach the end of their useful life and require replacement. Instead of one VIS Sign per station, TROI-Net Station Displays will be installed at more than one location at most stations. To meet accessibility requirements and like the current VIS Signs, TROI-Net Station Displays will provide the visual part of Metra's Audio/Visual announcements at stations. TROI-Net Station Displays will also provide live train tracking information, customer information messages, and emergency messages to Metra’s customers.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Displays continued delivery during this reporting period. Installation at 110 stations were completed with 285 monitors installed. Work continues with the installation of the displays.
Last Updated 06.10.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Stoney Creek Bridge- SWS | Track & Structure | Rail | $0 | $0 | Behind Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project funds engineering design services for the replacement of the Stoney Creek Bridge on Metra’s SouthWest Service. The bridge, constructed in 1917, spans over Stoney Creek in Oak Lawn at milepost 16.3. Construction funds are provided in future years.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The 100% design has been submitted to Metra and it is currently under review. Invitation for Bids is scheduled to be issued in June. The permit process activities are in progress.
Last Updated 06.10.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Substation Improvements - Matteson Substation | Support Facilities & Equipment | Rail | $0 | $0 | Behind Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project is for the replacement of the rectifiers at substations along the Metra Electric Line. The rectifiers are 35 years old and they have long exceeded their useful life. Replacement parts are not available. The Matteson Substation has been identified as a high priority location. Planned work at Matteson includes construction services to replace and add traction power equipment including a 15kv AC switchgear lineup and two?dry type copper?winding traction power transformers. Other locations identifed under this project include Jackson Substation and Homewood Substation.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The Contractor completed cable testing, rain test, and the prefabricated substation enclosure base sealing as well as mechanical field testing. Activities are ongoing for the second phase of functional testing. Procurement of long lead time items such as transfer switches and switch gears is ongoing.
Last Updated 06.10.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | CTA | Tactical Traction Power (Equipment/Cable/Enclosures) | Track & Structure | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
State of Good Repair projects and replacing obsolete equipment on CTA rail signal system
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The General Contractor completed construction activities and reached substantial completion during this reporting period. The contractor continues with punch list and closeout activities and final invoices remain. This will be the final update on this project.
Last Updated 06.10.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Ticket Vending Machines | Stations & Passenger Facilities | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project is the first phase of installing up to 310 ticket vending machines (TVMs) at selected stations throughout the Metra system to provide added amenities to Metra customers. The TVMs will offer a variety of ticket purchasing options and make purchasing tickets faster, easier, and more convenient for our customers. The TVMs will be fully ADA-accessible and will offer the ability to purchase tickets using contactless cards and mobile wallet applications and will no longer need to insert debit/credit cards into the machine.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
This project is currently in the production phase. Construction, delivery, and installation of the Ticket Vending Machines is in progress. A total of 247 machines have been installed.
Last Updated 06.10.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Ties & Ballast MED | Track & Structure | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
These projects consist of the replacement of cross ties, switch ties and ballast. In order to maintain proper track gauge and surface, it is necessary to replace ties and ballast periodically. This improves the riding quality of the trains and reduces the incidence of slow orders, which adversely affect adherence to train schedules. These projects represent part of an ongoing program to replace ties and ballast throughout the commuter territory.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Major elements for this project included ironworkers; track, signal and utilities work. Track and structure improvements were completed during this reporting period and final invoices remain. This will be the final update on this project.
Last Updated 04.01.2024 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Ties & Ballast MWD-W | Track & Structure | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Metra’s track renewal crew will rehabilitate dozens of miles of track along the Milwaukee District West (MD-W) Line in 2022. The project will be the most comprehensive investment in track conditions since Metra acquired the MD-W in 1987. Metra forces will Replace ties, clean or replace ballast, and replace switch components to provide smoother, faster, and safer track conditions. Metra partners with the Canadian Pacific Railroad to fund improvements to particular portions of the MD-W as freight train traffic degrade track conditions more rapidly than Metra trains.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Track and structure improvements were completed during this reporting period. Major elements include ironworkers; track, signal and utilities work. This will be the final update on this project.
Last Updated 06.10.2024 |