Project Management Oversight (PMO) Capital Projects
The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently. The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.
Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.
PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site. The latest report is the June 2023 Project Management Oversight report.
Agency | Project Title | Asset Category | Mode | 2025 Funding | 2025-2029 Funding | Status | |||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
+ | Metra | Ties & Ballast RID | Track & Structure | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
These projects consist of the replacement of cross ties, switch ties and ballast. In order to maintain proper track gauge and surface, it is necessary to replace ties and ballast periodically. This improves the riding quality of the trains and reduces the incidence of slow orders, which adversely affect adherence to train schedules. These projects represent part of an ongoing program to replace ties and ballast throughout the Rock Island District.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Major elements for this project includes ironworkers; track, signal and utilities work. Track and structure improvements completed during this reporting period. This will be the final update on this project.
Last Updated 06.10.2024 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | CTA | Traction Power Upgrades - Kedvale, Edmunds & Sacramento Substations | Track & Structure | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project will Provide for AC breaker replacement at Kedvale, Edmunds and Sacramento substations. This will also include the replacement of oil (non?PCB) transformer and rectifiers along with roof and doors replacement at the Kedvale and Sacramento substations.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The contractor was able to install the transformers, rectifiers, as well as roof and door replacements since the last reporting period. The project reachedsubstantial completion in January 2023 and punchlist items were completed. Final invoices remain. This will be the final update on this project.
Last Updated 06.22.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Pace | Transit Signal Priority (TSP) | Electrical, Signal & Communications | Bus | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Transit Signal Priority Integration - TSP implementation along priority corridors as part of the Regional Transit Signal Priority Implementation Program. Pace plans to deploy TSP along nine additional corridors at approximately 300 signalized intersections. The corridors include: 159th Street, Sibley Boulevard/147th Street, Roosevelt Road, Cicero Avenue, 95th Street, Grand Avenue (Lake County), Cermak Road, I-90 Transit Corridor Access Intersections and Halsted Street. This form represents the portion of the project funded with PAYGO in 2024. Years 2021-2023 of TSP related projects are funded with ICE funds as shown in Exhibit I.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The vendor received the permit to implement TSP system along 58 signalized intersections of Dempster Street from IDOT. TSP data and operations monitoring continued on Dempster Avenue, testing and TST data analysis continued on Grand Ave. as well as Roosevelt Road. TSP deployment was completed at 147th Street and 95th Street where the vendor continues testing. Cicero Ave. has TSP installation ongoing. The contractor is working on permit acquisitions for Cermak, Rand Road, and 159th.
Last Updated 06.10.2024 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Union Pacific West Line Expansion | Track & Structure | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project, a Public-Private Partnership between Metra and the Union Pacific Railroad, will construct two new segments of third mainline track on the Union Pacific West Line. One of the segments will be between the Vale Interlocking at milepost 10.0 in River Forest and the 25th Avenue Interlocking at milepost 11.8 in Melrose Park. The other segment will be between the Kress Interlocking at milepost 32.1 in West Chicago and the Peck Interlocking at milepost 38.4 in Geneva. Improvements are anticipated for all four of the interlockers that bookend the two segments. Additionally, a new interlocker may be constructed at milepost 35.4 between the Kress and Peck interlockers, which will increase operational flexibility. The interlocker improvements and additions will be constructed to meet Positive Train Control requirements. Improvements along both segments will include, but not be limited to, trackwork, earthwork, sub-ballast, structures, signal infrastructure, interlocking upgrades, and all work necessary at highway grade crossings. Bridge improvements will be needed over both the Des Plaines River and the Fox River to allow for the third mainline track. The project will also include platform relocations and improvements at both the Maywood and Melrose Park stations, and platform, platform shelter, and parking improvements at the Geneva station. Lastly, land acquisition may be required at various locations along the two segments in areas where the right of way is not wide enough to accommodate the third main track within the track centers required by the Union Pacific.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Construction activities on the western section of this project are in progress. Construction work included grading, sub-ballast layer installation, painting. The contractor finished paving Route 31, and it was opened to traffic. The contractor started backfilling on Fox River Bridge retaining wall to prepare for the third track and started demolishing the causeway. Additionally, the contractor finished Fox River Bridge piers repairs and started the excavation and preparation of the new track at 3rd Ave crossing (by Geneva Metra Station). Com Ed continued to relocate power poles.
Last Updated 09.25.2024 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | UP North Line - North 11 Bridges and Ravenswood Station | Track & Structure | Rail | $0 | $0 | Behind Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project involves the replacement of 22 bridges on the UP North Line in Chicago, Illinois. The structural scope of work will include, but not be limited to, replacement of existing stone abutments, retaining wall construction, steel spans, and decks. Also, some track work will be accomplished between the bridges, including the replacement of wood ties with concrete ties, and some commuter station modifications will be required, including the Ravenswood Station. To ensure reliable train operations, theproject will include various signal improvements, including: new interlockers at Addison Street (MP 5.0) and Rosehill (MP 7.3, between Balmoral Avenue and Bryn Mawr Avenue), and upgrades to the Deering interlocker (MP 3.2). In
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The bridge construction has been completed in September 2021. The station contractor reached substantial completion in August 2023. The contractor continues to address punch list items on the station. The station had a soft opening at the beginning of August and its opening ceremony at the beginning of October. This will be the final update of this project.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | CTA | Western Station Brown Line - Reconstruction | Stations & Passenger Facilities | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Rehabilitation required at this station that was not part of the Brown Line Reconstruction project and has older elevators that are part of the ASAP program on replacing existing elevators.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
CTA has reviewed the Design-Build Contractors pricing and technical proposals for the 60% design and 100% design for the Advance Work packages. The contractor will be expected to receive all permits necessary for the advance work by end of Q2-2024 and begin construction elements for the advance work when all permits are received.
Last Updated 06.10.2024 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Yard Improvements - Western Avenue | Support Facilities & Equipment | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project will provide design and construction funds for yard improvement projects at the yard facilities along the Milwaukee District lines. Upgrades under this project will include, but are not limited to, installation of electric heating elements for switches and the installation of steel grated boardwalks at the Western Avenue yard. Track work would include rail, ties, ballast and switches.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The diesel shop roof replacement and HVAC rehab completed the design and the IFB documents are being prepared. The Fox Lake cable reel and electrical components replacement continued construction activities in this reporting period. The Western Avenue yard water separator had the construction contract awarded and the contractor is obtaining permits as of this reporting period.
Last Updated 09.25.2024 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Zero-Emissions Locomotives | Rolling Stock | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Metra investment in innovative, cleaner energy locomotives will be funded in part by this project which will procure locomotives that produce zero mobile emissions. This multi-year, multi-phase project will acquire state-of-the-art technologies and pilot their performance capabilities given Metra’s track profile and the Chicago region’s inclement weather patterns. Metra estimates that replacing one old diesel locomotive with a zero-emission locomotive will reduce nitrogen oxides (NOx) emissions by more than 30 tons per year, thus significantly reducing the agency’s greenhouse gas footprint and greatly improving air quality in the region. Funds programmed in 2022 will finance engineering and design services for yard facilities to prepare for the new technology.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Metra put the bid on the street in May 2022 and was awarded to Stadler US, Inc. during this reporting period. The contract consists of eight trainsets for the base order. If Metra chooses to purchase additional trainsets, it can purchase up to eight (8) additional two-car battery powered self-propelled trainsets. In addition, Metra can also order up to 16 trailer cars with toilets and up to 16 trailer cars without toilets.
Last Updated 06.10.2024 |